917 1/2 W 48TH ST 90037
Certificate Information: 917 1/2 W 48TH ST 90037
- Application / Permit
- 21016-10000-58894
- Plan Check / Job No.
- B21LA23901
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- TO CONVERT (E) RECREATION ROOM INTO AN ACCESSORY DWELLING UNIT ADU Per WFPP Per: GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)(d)(g)
- Permit Issued
- Issued on 4/7/2023
- Issuing Office
- Metro
- Current Status
- Issued on 4/7/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2022 | KHUONG TRUONG |
| Corrections Issued | 1/14/2022 | KHUONG TRUONG |
| Building Plans Picked Up | 1/18/2022 | APPLICANT |
| Applicant returned to address corrections | 3/16/2022 | SHANGQIN XIE |
| Applicant returned to address corrections | 3/28/2023 | DANIEL SANJUAN |
| Applicant returned to address corrections | 4/3/2023 | CRISTINA SALAZAR |
| Plan Check Approved | 4/5/2023 | JOSEPH RAFOLS |
| Issued | 4/7/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/20/2023 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 3/20/2023 | STEVE MELGAR |
| Sewer availability | Cleared | 3/20/2023 | STEVE MELGAR |
| Tenant Habitability Plan | Cleared | 4/5/2023 | JORGE ALCANTAR |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/6/2023 | Not Ready for Inspection | SABAS ALONSO |
| Final | 6/6/2023 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 6/6/2023 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 6/6/2023 | Not Ready for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 6/28/2023 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 7/6/2023 | Corrections Issued | SABAS ALONSO |
| Green Building Rough | 7/6/2023 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 7/6/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 7/6/2023 | Corrections Issued | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/15/2023 | Corrections Issued | SABAS ALONSO |
| Final | 8/15/2023 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 8/15/2023 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 8/15/2023 | Approved | SABAS ALONSO |
| Final | 8/30/2023 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Rough | 8/30/2023 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 9/18/2023 | No Access for Inspection | SABAS ALONSO |
| Final | 9/18/2023 | No Access for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 9/20/2023 | No Access for Inspection | SABAS ALONSO |
| Final | 9/25/2023 | Corrections Issued | SABAS ALONSO |
| Gas Test | 9/28/2023 | Corrections Issued | RONNIE MINDANAO |
| Insulation | 9/28/2023 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Rough | 9/28/2023 | Corrections Issued | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 10/2/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 10/2/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| Gas Test | 10/2/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| Insulation | 10/2/2023 | Partial Approval | JUSTIN HAWLEY |
| PLUMBING-Rough | 10/2/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| Special/Order Compliance | 10/2/2023 | Corrections Issued | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 10/5/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 10/5/2023 | Approved | SABAS ALONSO |
| Deputy Drilled-In Anchors | 3/29/2024 | No Access for Inspection | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 4/1/2024 | Corrections Issued | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 4/9/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2024 | Corrections Issued | CRAIG DAVIS |
| Wood Frame | 5/1/2024 | Corrections Issued | CRAIG DAVIS |
| BUILDING-Rough-Frame | 5/9/2024 | Partial Approval | CRAIG DAVIS |
| ELECTRICAL-Rough | 5/9/2024 | Corrections Issued | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2024 | Partial Approval | CRAIG DAVIS |
| Wood Frame | 5/9/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2024 | Partial Approval | CRAIG DAVIS |
| Insulation | 5/21/2024 | Partial Approval | CRAIG DAVIS |
| Interior/Exterior Lathing | 5/21/2024 | Approved | CRAIG DAVIS |
| Drywall Nailing | 6/10/2024 | No Access for Inspection | BRENDAN MORELLI |
| Drywall Nailing | 6/11/2024 | Conditional Approval | DARRYL ARNOLD |
| BUILDING-Rough-Frame | 7/18/2024 | Conditional Approval | DARRYL ARNOLD |
| Final | 7/18/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| BUILDING-Rough-Frame | 7/22/2024 | Approved | ANTHONY EGSON |
| Final | 7/22/2024 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Final | 8/7/2024 | Corrections Issued | CRAIG DAVIS |
| Final | 8/7/2024 | Corrections Issued | CRAIG DAVIS |
| Final | 8/21/2024 | Partial Approval | CRAIG DAVIS |