3849 S HARVARD BLVD 90062
Certificate Information: 3849 S HARVARD BLVD 90062
- Application / Permit
- 21016-10000-58743
- Plan Check / Job No.
- B21LA23754
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED [24 X 24] GARAGE TO ONE BEDROOM ADU PER WFPP. NO ONSITE PARKING PROVIDED.
- Permit Issued
- Issued on 7/6/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/28/2021 | GEORGE ALVAREZ |
| Corrections Issued | 1/10/2022 | GEORGE ALVAREZ |
| Plan Check Approved | 4/11/2022 | JESSE JIMENEZ |
| Building Plans Picked Up | 6/7/2022 | APPLICANT |
| Issued | 7/6/2022 | APPLICANT |
| CofO in Progress | 12/29/2022 | SABAS ALONSO |
| CofO Issued | 1/4/2023 | DEROLD HAUFF |
| Permit Finaled | 1/4/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/22/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 2/22/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2022 | STEVE MELGAR |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/19/2022 | Approved | ALEJANDRO DE ARTOLA |
| Deputy Drilled-In Anchors | 8/17/2022 | Conditional Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 8/18/2022 | Not Ready for Inspection | SABAS ALONSO |
| Deputy Drilled-In Anchors | 8/23/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 8/23/2022 | Approved | HORACE FULTZ |
| Underground Mechanical | 8/31/2022 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 9/6/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 9/16/2022 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 9/16/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 9/16/2022 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 9/16/2022 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 9/23/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 9/23/2022 | Approved | SABAS ALONSO |
| HVAC-Rough | 9/23/2022 | Approved | SABAS ALONSO |
| Insulation | 9/28/2022 | Approved | HORACE FULTZ |
| Drywall Nailing | 10/3/2022 | Not Ready for Inspection | RYAN SALAZAR |
| Interior/Exterior Lathing | 10/3/2022 | Not Ready for Inspection | RYAN SALAZAR |
| Drywall Nailing | 10/7/2022 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 10/7/2022 | Approved | SABAS ALONSO |
| Final | 11/17/2022 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 11/17/2022 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/17/2022 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 11/17/2022 | Not Required | SABAS ALONSO |
| Smoke Detectors | 11/17/2022 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 12/15/2022 | Approved | SABAS ALONSO |
| Final | 12/15/2022 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Final | 12/15/2022 | Approved | SABAS ALONSO |
| Final | 12/20/2022 | Corrections Issued | SABAS ALONSO |
| Final | 12/28/2022 | OK to Issue CofO | SABAS ALONSO |