3849 S HARVARD BLVD 90062

Certificate Information: 3849 S HARVARD BLVD 90062

Application / Permit
21016-10000-58743
Plan Check / Job No.
B21LA23754
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED [24 X 24] GARAGE TO ONE BEDROOM ADU PER WFPP. NO ONSITE PARKING PROVIDED.
Permit Issued
Issued on 7/6/2022
Issuing Office
Metro
Current Status
CofO Issued on 1/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2021 APPLICANT
Assigned to Plan Check Engineer 12/28/2021 GEORGE ALVAREZ
Corrections Issued 1/10/2022 GEORGE ALVAREZ
Plan Check Approved 4/11/2022 JESSE JIMENEZ
Building Plans Picked Up 6/7/2022 APPLICANT
Issued 7/6/2022 APPLICANT
CofO in Progress 12/29/2022 SABAS ALONSO
CofO Issued 1/4/2023 DEROLD HAUFF
Permit Finaled 1/4/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/22/2022 STEVE MELGAR
Sewer availability Cleared 2/22/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 2/24/2022 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/19/2022 Approved ALEJANDRO DE ARTOLA
Deputy Drilled-In Anchors 8/17/2022 Conditional Approval SABAS ALONSO
Footing/Foundation/Slab 8/18/2022 Not Ready for Inspection SABAS ALONSO
Deputy Drilled-In Anchors 8/23/2022 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 8/23/2022 Approved HORACE FULTZ
Underground Mechanical 8/31/2022 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 9/6/2022 Not Ready for Inspection SHAVONNE ESPINOZA
BUILDING-Rough-Frame 9/16/2022 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 9/16/2022 Approved SABAS ALONSO
Green Building Rough 9/16/2022 Corrections Issued SABAS ALONSO
PLUMBING-Rough 9/16/2022 Approved SABAS ALONSO
BUILDING-Rough-Frame 9/23/2022 Approved SABAS ALONSO
Green Building Rough 9/23/2022 Approved SABAS ALONSO
HVAC-Rough 9/23/2022 Approved SABAS ALONSO
Insulation 9/28/2022 Approved HORACE FULTZ
Drywall Nailing 10/3/2022 Not Ready for Inspection RYAN SALAZAR
Interior/Exterior Lathing 10/3/2022 Not Ready for Inspection RYAN SALAZAR
Drywall Nailing 10/7/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 10/7/2022 Approved SABAS ALONSO
Final 11/17/2022 Corrections Issued SABAS ALONSO
Green Building Final 11/17/2022 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 11/17/2022 SGSOV Approved SABAS ALONSO
Service/Power Release 11/17/2022 Not Required SABAS ALONSO
Smoke Detectors 11/17/2022 Approved SABAS ALONSO
ELECTRICAL-Final 12/15/2022 Approved SABAS ALONSO
Final 12/15/2022 Corrections Issued SABAS ALONSO
PLUMBING-Final 12/15/2022 Approved SABAS ALONSO
Final 12/20/2022 Corrections Issued SABAS ALONSO
Final 12/28/2022 OK to Issue CofO SABAS ALONSO