5730 N COSTELLO AVE 91401

Certificate Information: 5730 N COSTELLO AVE 91401

Application / Permit
21016-10000-58734
Plan Check / Job No.
B21LA23737
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF (E) GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 4/7/2022
Issuing Office
Current Status
CofO Issued on 12/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/28/2021 APPLICANT
Assigned to Plan Check Engineer 1/6/2022 LAMAR DAVIS
Corrections Issued 1/11/2022 LAMAR DAVIS
Quality Review Completed 1/19/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 2/15/2022 LAMAR DAVIS
Plan Check Approved 4/5/2022 LAMAR DAVIS
Issued 4/7/2022 APPLICANT
Building Plans Picked Up 4/13/2022 APPLICANT
CofO in Progress 11/29/2022 RYAN SALAZAR
Permit Finaled 12/17/2022 MICHAEL SMITH
CofO Issued 12/17/2022 MICHAEL SMITH
Permit Finaled 12/17/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/27/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 1/27/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 1/27/2022 DAGOVERTO GUERRERO
Construction near power lines Cleared 3/23/2022 RIDWAN HARDY
Hold Cleared 4/18/2022 JASON SHEETS

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Test 5/23/2022 Partial Approval ALAN MORELOS
PLUMBING-Rough 5/23/2022 Approved ALAN MORELOS
Sewer 5/23/2022 Approved ALAN MORELOS
Underground Mechanical 5/23/2022 Approved ALAN MORELOS
Footing/Foundation/Slab 5/26/2022 Approved RAUL OLAGI
HVAC-Rough 6/10/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 6/10/2022 Approved RICHARD DOCKUS
ELECTRICAL-Rough 6/15/2022 Approved RICHARD DOCKUS
Sewer 6/15/2022 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 6/22/2022 Approved RICHARD DOCKUS
Green Building Rough 6/22/2022 Approved RICHARD DOCKUS
Interior/Exterior Lathing 6/28/2022 Approved WILLIAM WREN
Insulation 7/5/2022 Corrections Issued ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 7/11/2022 Approved RICHARD DOCKUS
Insulation 7/11/2022 Approved RICHARD DOCKUS
Interior/Exterior Lathing 7/26/2022 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 10/25/2022 Approved RICHARD DOCKUS
Final 10/25/2022 Corrections Issued RICHARD DOCKUS
Green Building Final 10/25/2022 Approved RICHARD DOCKUS
HVAC-Final 10/25/2022 Approved RICHARD DOCKUS
PLUMBING-Final 10/25/2022 Corrections Issued RICHARD DOCKUS
Smoke Detectors 10/25/2022 Approved RICHARD DOCKUS
ELECTRICAL-Final 10/31/2022 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 10/31/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 11/14/2022 Approved RICHARD DOCKUS
Final 11/14/2022 Corrections Issued RICHARD DOCKUS
HVAC-Final 11/14/2022 Approved RICHARD DOCKUS
PLUMBING-Final 11/14/2022 Approved RICHARD DOCKUS
ELECTRICAL-Final 11/18/2022 Approved THOMAS FINNILA
Final 11/28/2022 OK to Issue CofO RYAN SALAZAR