5730 N COSTELLO AVE 91401
Certificate Information: 5730 N COSTELLO AVE 91401
- Application / Permit
- 21016-10000-58734
- Plan Check / Job No.
- B21LA23737
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF (E) GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 4/7/2022
- Issuing Office
- Current Status
- CofO Issued on 12/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2022 | LAMAR DAVIS |
| Corrections Issued | 1/11/2022 | LAMAR DAVIS |
| Quality Review Completed | 1/19/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 2/15/2022 | LAMAR DAVIS |
| Plan Check Approved | 4/5/2022 | LAMAR DAVIS |
| Issued | 4/7/2022 | APPLICANT |
| Building Plans Picked Up | 4/13/2022 | APPLICANT |
| CofO in Progress | 11/29/2022 | RYAN SALAZAR |
| Permit Finaled | 12/17/2022 | MICHAEL SMITH |
| CofO Issued | 12/17/2022 | MICHAEL SMITH |
| Permit Finaled | 12/17/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/27/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 1/27/2022 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 3/23/2022 | RIDWAN HARDY |
| Hold | Cleared | 4/18/2022 | JASON SHEETS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Test | 5/23/2022 | Partial Approval | ALAN MORELOS |
| PLUMBING-Rough | 5/23/2022 | Approved | ALAN MORELOS |
| Sewer | 5/23/2022 | Approved | ALAN MORELOS |
| Underground Mechanical | 5/23/2022 | Approved | ALAN MORELOS |
| Footing/Foundation/Slab | 5/26/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 6/10/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 6/10/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Rough | 6/15/2022 | Approved | RICHARD DOCKUS |
| Sewer | 6/15/2022 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 6/22/2022 | Approved | RICHARD DOCKUS |
| Green Building Rough | 6/22/2022 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 6/28/2022 | Approved | WILLIAM WREN |
| Insulation | 7/5/2022 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2022 | Approved | RICHARD DOCKUS |
| Insulation | 7/11/2022 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 7/26/2022 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 10/25/2022 | Approved | RICHARD DOCKUS |
| Final | 10/25/2022 | Corrections Issued | RICHARD DOCKUS |
| Green Building Final | 10/25/2022 | Approved | RICHARD DOCKUS |
| HVAC-Final | 10/25/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 10/25/2022 | Corrections Issued | RICHARD DOCKUS |
| Smoke Detectors | 10/25/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 10/31/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 10/31/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 11/14/2022 | Approved | RICHARD DOCKUS |
| Final | 11/14/2022 | Corrections Issued | RICHARD DOCKUS |
| HVAC-Final | 11/14/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 11/14/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 11/18/2022 | Approved | THOMAS FINNILA |
| Final | 11/28/2022 | OK to Issue CofO | RYAN SALAZAR |