3112 S BENTLEY AVE 90034

Certificate Information: 3112 S BENTLEY AVE 90034

Application / Permit
21016-10000-58732
Plan Check / Job No.
B21LA23739
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
IRREGULAR ADDITION TO AN EXISTING SINGLE FAMILY DWELLING. TO ADD A TRELLIS TO THE FRONT AND REAR OF DWELLING, AND ADD A 2ND FLOOR TO THE EXISTING DWELLING. INTERIOR AND EXTERIOR ALTERATION TO CHANGE FLOOR LAYOUT AND CREATE NEW DOORS AND WINDOWS. BUILDING TO BE SPRINKLERED 1 OF 2
Permit Issued
Issued on 10/4/2022
Issuing Office
Valley
Current Status
CofO Issued on 2/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2021 APPLICANT
Assigned to Plan Check Engineer 1/20/2022 MINA HABIB
Corrections Issued 2/11/2022 MINA HABIB
Quality Review Completed 2/17/2022 FARUK SEZER
Building Plans Picked Up 3/4/2022 APPLICANT
Applicant returned to address corrections 3/17/2022 MINA HABIB
Applicant returned to address corrections 6/3/2022 MINA HABIB
Applicant returned to address corrections 6/17/2022 MINA HABIB
Applicant returned to address corrections 8/8/2022 MINA HABIB
Applicant returned to address corrections 9/6/2022 MINA HABIB
Plan Check Approved 9/14/2022 MINA HABIB
Issued 10/4/2022 APPLICANT
CofO in Progress 2/26/2024 JESUS PINEDA
Permit Finaled 2/29/2024 DANIEL ORRANTE
CofO Issued 2/29/2024 DANIEL ORRANTE
Permit Finaled 2/29/2024 DANIEL ORRANTE

Permit Application Clearance Information

Hydrant and Access approval Cleared 4/22/2022 DWAYNE LAURENT
Eng Process Fee Ord 176,300 Cleared 5/24/2022 JENSON LEE
Sewer availability Cleared 5/24/2022 JENSON LEE
Construction near power lines Cleared 6/8/2022 RIDWAN HARDY
Construction within easement Cleared 6/8/2022 RIDWAN HARDY
GPI Written Notices Cleared 8/8/2022 MINA HABIB
Grading Pre-Inspection Cleared 8/8/2022 MINA HABIB
Green Code Cleared 8/8/2022 MINA HABIB
Specific Plan Cleared 8/9/2022 COLLINS ALLAN
Low Impact Development Cleared 9/6/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 9/9/2022 JENSON LEE

Contact Information

Architect Contento,, Lindsey Sherman; Lic. No.: C36546 3693 BUCKINGHAM ROAD      LOS ANGELES, CA 90016
Contractor Makeover Builders Inc; Lic. No.: 986740-B 21781 VENTURA BLVD UNIT 634      WOODLAND HILLS, CA 91364
Engineer Tan,, Henreik Steven; Lic. No.: C65723 5100 LLANO DRIVE      WOODLAND HILLS, CA 91364

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/23/2022 Partial Approval JOHNNY MIRANDA
Deputy Reinf. Concrete 2/27/2023 Conditional Approval JOHNNY MIRANDA
Deputy Wood Construction 2/28/2023 No Access for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 3/1/2023 Not Ready for Inspection CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 3/7/2023 Approved JOHNNY MIRANDA
HVAC-Rough 4/10/2023 Corrections Issued DAVID FEILER
Interior/Exterior Lathing 4/12/2023 Partial Approval HERBERT GIRON
HVAC-Rough 4/17/2023 Approved JOHNNY MIRANDA
ELECTRICAL-Rough 5/9/2023 Approved JOHNNY MIRANDA
Gas Test 5/9/2023 Approved JOHNNY MIRANDA
PLUMBING-Rough 5/9/2023 Approved JOHNNY MIRANDA
Insulation 5/15/2023 Approved JOHNNY MIRANDA
Drywall Nailing 6/2/2023 Approved JOHNNY MIRANDA
Green Building Rough 6/2/2023 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 6/2/2023 Approved JOHNNY MIRANDA
Shower Pan 6/2/2023 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 2/21/2024 Approved JESUS PINEDA
Final 2/21/2024 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 2/21/2024 Approved JESUS PINEDA
Green Building Final 2/21/2024 Approved JESUS PINEDA
MERV13>=Final 2/21/2024 Approved JESUS PINEDA
MERV13>=Rough 2/21/2024 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 2/21/2024 SGSOV Approved JESUS PINEDA
Smoke Detectors 2/21/2024 Approved JESUS PINEDA
Final 2/26/2024 OK to Issue CofO JESUS PINEDA