1974 S COMSTOCK AVE 90025
Certificate Information: 1974 S COMSTOCK AVE 90025
- Application / Permit
- 21016-10000-58727
- Plan Check / Job No.
- B21LA23732
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL OF EXISTING SINGLE FAMILY DWELLING. EXTERIOR ALTERATIONS, NEW EXTERIOR OPENINGS, NEW WINDOWS, EXTERIOR WALL DEMO AND INFILL. DEMO INTERIOR WALLS AND NEW CEILING BEAMS, PAD FOOTINGS, AND SHEAR WALLS.
- Permit Issued
- Issued on 3/10/2022
- Issuing Office
- Current Status
- Permit Finaled on 8/31/2023
Permit Application Status History
| Submitted | 12/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/28/2021 | GEORGE ALVAREZ |
| Corrections Issued | 1/10/2022 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 2/23/2022 | GEORGE ALVAREZ |
| Plan Check Approved | 2/28/2022 | GEORGE ALVAREZ |
| Issued | 3/10/2022 | APPLICANT |
| Building Plans Picked Up | 3/14/2022 | APPLICANT |
| Permit Finaled | 8/31/2023 | STEPHANIE SWANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/11/2022 | PATRICK MISCHLICH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baich,, Brendon Chad; Lic. No.: C83347 | PO BOX 8840 POMONA, CA 91701 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/29/2022 | Partial Approval | BRENDAN LOONEY |
| Deputy Other (see comments) | 3/30/2022 | Approved | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 3/30/2022 | Approved | MICHAEL PELHAM |
| Footing/Foundation/Slab | 3/31/2022 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 7/5/2022 | Partial Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 7/5/2022 | Corrections Issued | KEVIN SARGSYAN |
| Gas Test | 7/5/2022 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 7/5/2022 | Corrections Issued | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 7/28/2022 | Corrections Issued | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 9/26/2022 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 9/26/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 9/26/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 9/26/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 10/26/2022 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 10/26/2022 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 10/26/2022 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 10/26/2022 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 11/4/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 11/4/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 11/4/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 11/23/2022 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 12/5/2022 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 12/5/2022 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 12/5/2022 | Approved | STEPHANIE SWANSON |
| Insulation | 12/13/2022 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 12/23/2022 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 1/30/2023 | No Access for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Shower Pan | 3/6/2023 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 3/10/2023 | Partial Approval | MICHAEL PELHAM |
| Shower Pan | 3/10/2023 | Approved | MICHAEL PELHAM |
| ELECTRICAL-Final | 6/23/2023 | Approved | BRENDAN LOONEY |
| Final | 6/23/2023 | Corrections Issued | BRENDAN LOONEY |
| HVAC-Final | 6/23/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Final | 6/23/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 6/23/2023 | SGSOV Not Ready | BRENDAN LOONEY |
| Smoke Detectors | 6/23/2023 | Approved | BRENDAN LOONEY |
| Final | 8/28/2023 | Corrections Issued | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 8/28/2023 | SGSOV Not Ready | STEPHANIE SWANSON |
| Final | 8/31/2023 | Permit Finaled | STEPHANIE SWANSON |
| Gas Test | 8/31/2023 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 8/31/2023 | SGSOV Approved | STEPHANIE SWANSON |