12439 W HUSTON ST 91607
Certificate Information: 12439 W HUSTON ST 91607
- Application / Permit
- 21016-10000-58715
- Plan Check / Job No.
- B21LA23720
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2ND FLOOR ADDITION TO AN (E) S.F.D WITH AN ATTACHED GARAGEOVER (E) GARAGE AND PORCH
- Permit Issued
- Issued on 1/4/2024
- Issuing Office
- Metro
- Current Status
- Issued on 1/4/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2022 | MINA HABIB |
| Corrections Issued | 3/25/2022 | MINA HABIB |
| Quality Review Completed | 4/5/2022 | FARUK SEZER |
| Building Plans Picked Up | 4/7/2022 | APPLICANT |
| Applicant returned to address corrections | 1/18/2023 | MINA HABIB |
| Applicant returned to address corrections | 4/20/2023 | MINA HABIB |
| Applicant returned to address corrections | 5/23/2023 | MINA HABIB |
| Plan Check Approved | 6/20/2023 | MINA HABIB |
| Issued | 1/4/2024 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2023 | WALLIE JONG |
| Sewer availability | Cleared | 3/2/2023 | WALLIE JONG |
| Low Impact Development | Cleared | 3/10/2023 | TOMMY YIN |
| Specific Plan | Cleared | 3/13/2023 | CHRISTIAN PEARSON |
| Roof/Waste drainage to street | Cleared | 3/14/2023 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 3/17/2023 | GILBERT URREA |
| Private street | Cleared | 3/22/2023 | RUBEN VASQUEZ |
| Green Code | Cleared | 5/23/2023 | MINA HABIB |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/8/2024 | Conditional Approval | JOSE AVILA |
| Footing/Foundation/Slab | 3/13/2024 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 3/26/2024 | Approved | JOSE AVILA |
| Deputy Drilled-In Anchors | 4/1/2024 | Conditional Approval | JUAN VALENZUELA |
| Special/Order Compliance | 4/4/2024 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2024 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 11/4/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Rough | 11/4/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 11/4/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| MERV13>=Rough | 11/4/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 12/5/2024 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 12/5/2024 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 12/5/2024 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 12/19/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Rough | 12/19/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| MERV13>=Rough | 12/19/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2025 | No Access for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2025 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 3/5/2025 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 3/10/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Rough | 3/10/2025 | Approved | GAREN HAYRAPETYAN |
| MERV13>=Rough | 3/10/2025 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 4/4/2025 | Approved | OGANES TARAKHCHYAN |
| Insulation | 4/14/2025 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 4/21/2025 | Approved | RYAN SALAZAR |