1324 W 57TH ST 1-17 90037

Certificate Information: 1324 W 57TH ST 1-17 90037

Application / Permit
21016-10000-58675
Plan Check / Job No.
B21LA23677
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONVERSION OF (E) GARAGE/CARPORT TO ADU PER GCS 65852.2(e)(1)(C) (SOFT STORY PERMIT OBTAINED UNDER DIFFERENT PERMIT NO. 21016-10000-25679). **3 NEW ADU**
Permit Issued
Issued on 4/3/2025
Issuing Office
Metro
Current Status
CofO Issued on 6/8/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/8/2022 APPLICANT
Assigned to Plan Check Engineer 1/27/2022 VARAND SARKISIAN
Corrections Issued 2/1/2022 VARAND SARKISIAN
Quality Review Completed 2/7/2022 HANS SANTIAGO
Building Plans Picked Up 2/10/2022 APPLICANT
Applicant returned to address corrections 6/20/2024 VARAND SARKISIAN
Plan Check Approved 8/15/2024 VARAND SARKISIAN
Issued 4/3/2025 APPLICANT
CofO in Progress 5/28/2026 ALFREDO LOPEZ
Permit Finaled 6/8/2026 RAFAEL ESPINOZA
CofO Issued 6/8/2026 RAFAEL ESPINOZA
Permit Finaled 6/8/2026 RAFAEL ESPINOZA

Permit Application Clearance Information

Address approval Cleared 6/20/2023 CELINA MORENO
Sewer availability Cleared 6/20/2023 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 6/23/2023 CELINA MORENO
DAS Clearance Cleared 2/7/2024 VARAND SARKISIAN
Green Code Cleared 7/30/2024 AARON COSTA
Tenant Habitability Plan Cleared 8/15/2024 RICARDO BOHORQUEZ

Contact Information

Contractor Josiah P Inc; Lic. No.: 1075920-B 2737 W FRANCIS AVENUE APT #307      LOS ANGELES, CA 90005
Engineer Medina,, Ferdinand Casaclang; Lic. No.: C88007 1051 S HOLT AVE APT F      LOS ANGELES, CA 90035

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/8/2025 Conditional Approval DARRYL ARNOLD
Excavation/Setback/Form/Re-Bar 5/12/2025 Approved ALFREDO LOPEZ
Footing/Foundation/Slab 5/12/2025 Approved ALFREDO LOPEZ
Floor/Roof Diaphrgm/Shear Wall 6/2/2025 Partial Approval ALFREDO LOPEZ
Structural Steel Frame 6/2/2025 Partial Approval ALFREDO LOPEZ
Wood Frame 6/2/2025 Partial Inspection ALFREDO LOPEZ
Interior/Exterior Lathing 7/11/2025 Approved ALFREDO LOPEZ
Insulation 9/2/2025 Approved ALFREDO LOPEZ
Wood Frame 9/2/2025 Approved ALFREDO LOPEZ
Drywall Nailing 9/5/2025 Approved ALFREDO LOPEZ
Interior/Exterior Lathing 9/22/2025 Conditional Approval DARRYL ARNOLD
Final 1/5/2026 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 1/5/2026 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 1/5/2026 Conditional Approval DARRYL ARNOLD
Final 3/19/2026 OK to Issue CofO ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 3/19/2026 SGSOV Not Required ALFREDO LOPEZ
Smoke Detectors 3/19/2026 Approved ALFREDO LOPEZ
Final 4/15/2026 Conditional Approval DARRYL ARNOLD
Smoke Detectors 4/15/2026 Approved DARRYL ARNOLD