4767-4769 W MARATHON ST 90029
Certificate Information: 4767-4769 W MARATHON ST 90029
- Application / Permit
- 21016-10000-58669
- Plan Check / Job No.
- B21LA23670
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT ATTACHED 4-CAR CARPORT INTO (2) ADU'S PER STATE LAW [4767 & 4769 W MARATHON ST].
- Permit Issued
- Issued on 8/30/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2021 | LAWRENCE QUIRANTE |
| Corrections Issued | 1/1/2022 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 1/4/2022 | APPLICANT |
| Plan Check Approved | 5/5/2022 | GEORGE ALVAREZ |
| Issued | 8/30/2022 | APPLICANT |
| CofO in Progress | 1/27/2023 | ERNESTO CORRAL |
| CofO Issued | 1/27/2023 | ERNESTO CORRAL |
| Permit Finaled | 1/27/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 1/3/2022 | KHOUNG LE |
| Sewer availability | Cleared | 1/3/2022 | KHOUNG LE |
| Eng Process Fee Ord 176,300 | Cleared | 1/12/2022 | KHOUNG LE |
Contact Information
| Contractor | Rent Ready Construction Inc; Lic. No.: 1065376-B | 631 N SIERRA BONITA AVE LOS ANGELES, CA 90036 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/23/2022 | Approved | GREGORY POMISH |
| Deputy Drilled-In Anchors | 9/28/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Green Building Rough | 10/19/2022 | Not Ready for Inspection | JONATHAN QUACH |
| Wood Frame | 10/19/2022 | Partial Inspection | JONATHAN QUACH |
| Insulation | 11/1/2022 | Approved | JONATHAN QUACH |
| Interior/Exterior Lathing | 11/1/2022 | Partial Approval | JONATHAN QUACH |
| Drywall Nailing | 11/7/2022 | Approved | JONATHAN QUACH |
| Interior/Exterior Lathing | 11/10/2022 | Approved | JONATHAN QUACH |
| Final | 1/18/2023 | Partial Inspection | RONALD JIMENEZ |
| Green Building Final | 1/18/2023 | Partial Inspection | RONALD JIMENEZ |
| Green Building Rough | 1/18/2023 | Approved | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 1/18/2023 | SGSOV Approved | RONALD JIMENEZ |
| Smoke Detectors | 1/18/2023 | Approved | RONALD JIMENEZ |
| Wood Frame | 1/18/2023 | Approved | RONALD JIMENEZ |
| Final | 1/27/2023 | OK to Issue CofO | RONALD JIMENEZ |
| Green Building Final | 1/27/2023 | Approved | RONALD JIMENEZ |