5713 S BRYNHURST AVE 90043

Certificate Information: 5713 S BRYNHURST AVE 90043

Application / Permit
21016-10000-58662
Plan Check / Job No.
B21LA23665
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: CONVERT (E) GARAGE TO 1-STORY ACCESSOY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 3/22/2022
Issuing Office
Current Status
CofO Issued on 4/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/22/2021 APPLICANT
Assigned to Plan Check Engineer 12/22/2021 DANIEL YIP
Corrections Issued 12/23/2021 DANIEL YIP
Applicant returned to address corrections 2/3/2022 DANIEL YIP
Applicant returned to address corrections 3/9/2022 DANIEL YIP
Applicant returned to address corrections 3/16/2022 DANIEL YIP
Plan Check Approved 3/21/2022 DANIEL YIP
Issued 3/22/2022 APPLICANT
CofO in Progress 4/19/2023 ALIZAH MAYAGOITIA
No Progress 4/19/2023 SCOTT FINNILA
CofO in Progress 4/20/2023 SCOTT FINNILA
CofO in Progress 4/20/2023 SCOTT FINNILA
Permit Finaled 4/23/2023 DEROLD HAUFF
CofO Issued 4/23/2023 DEROLD HAUFF
Permit Finaled 4/23/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/22/2022 CELINA MORENO
Sewer availability Cleared 2/22/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 3/1/2022 CELINA MORENO

Contact Information

Contractor Tolbert Construction; Lic. No.: 498836-B PO BOX 44349      LOS ANGELES, CA 90044

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/29/2022 Partial Inspection ANTHONY EGSON
Deputy Drilled-In Anchors 4/20/2022 Approved ANTHONY EGSON
Footing/Foundation/Slab 4/25/2022 Approved ANTHONY EGSON
Insulation 4/27/2022 Approved ANTHONY EGSON
Drywall Nailing 5/6/2022 Approved ANTHONY EGSON
Green Building Rough 5/6/2022 Approved ANTHONY EGSON
Interior/Exterior Lathing 5/6/2022 Approved ANTHONY EGSON
Final 7/29/2022 Corrections Issued ANTHONY EGSON
Green Building Final 7/29/2022 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 7/29/2022 SGSOV Not Ready ANTHONY EGSON
Smoke Detectors 7/29/2022 Approved ANTHONY EGSON
Final 8/31/2022 Corrections Issued ANTHONY EGSON
Green Building Final 8/31/2022 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 8/31/2022 SGSOV Not Ready ANTHONY EGSON
Wood Frame 8/31/2022 Approved ANTHONY EGSON
Final 2/27/2023 Not Ready for Inspection ANTHONY EGSON
Green Building Final 2/27/2023 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 2/27/2023 SGSOV Approved ANTHONY EGSON
Final 4/10/2023 Partial Inspection MICHAEL LEWIS
Green Building Final 4/10/2023 Approved MICHAEL LEWIS
Final 4/18/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 4/19/2023 OK to Issue CofO ALIZAH MAYAGOITIA