3321 S BEVERLY DR 90034

Certificate Information: 3321 S BEVERLY DR 90034

Application / Permit
21016-10000-58592
Plan Check / Job No.
B21LA23609
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*EPLAN* CONVERT (E) ATTACHED GARAGE (14' X 40') TO ADU PER CA GC 65852.2(e)(1)(A).
Permit Issued
Issued on 11/18/2024
Issuing Office
Current Status
CofO Issued on 5/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/28/2021 APPLICANT
Assigned to Plan Check Engineer 12/29/2021 VIVIAN LAO
Corrections Issued 12/30/2021 VIVIAN LAO
Applicant returned to address corrections 1/19/2022 VIVIAN LAO
Plan Check Approved 1/26/2022 VIVIAN LAO
Issued 11/18/2024 APPLICANT
CofO in Progress 5/9/2025 BOBBY KEY
Permit Finaled 5/13/2025 RICHARD STEINBACH
CofO Issued 5/13/2025 RICHARD STEINBACH
Permit Finaled 5/13/2025 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 1/12/2022 DYLAN SITTIG
Address approval Cleared 1/15/2022 SAUL GARCIA
Roof/Waste drainage to street Cleared 1/15/2022 SAUL GARCIA
Sewer availability Cleared 1/15/2022 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 1/18/2022 SAUL GARCIA

Contact Information

Contractor Oc Builders Group Inc; Lic. No.: 1052090-B       ,

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/20/2024 Partial Approval ASHLEY THOMPSON
Pre-Inspection 1/14/2025 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 1/17/2025 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 2/13/2025 Approved DANIEL VERA
Deputy Drilled-In Anchors 2/24/2025 Conditional Approval ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 3/3/2025 Corrections Issued ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 3/4/2025 Partial Approval ASHLEY THOMPSON
Wood Frame 3/5/2025 Not Ready for Inspection KIRK SANDERS
Wood Frame 3/10/2025 Not Ready for Inspection ASHLEY THOMPSON
Insulation 3/12/2025 Approved JAYLIN GRAVITTE
Floor/Roof Diaphrgm/Shear Wall 3/14/2025 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 3/17/2025 Not Ready for Inspection ASHLEY THOMPSON
Drywall Nailing 3/19/2025 Partial Approval ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 3/19/2025 Approved ASHLEY THOMPSON
Drywall Nailing 3/21/2025 Approved JAYLIN GRAVITTE
Final 4/25/2025 Not Ready for Inspection ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 4/25/2025 SGSOV Not Ready ASHLEY THOMPSON
Smoke Detectors 4/25/2025 Not Ready for Inspection ASHLEY THOMPSON
Wood Frame 4/25/2025 Approved ASHLEY THOMPSON
Final 5/6/2025 Corrections Issued MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 5/6/2025 SGSOV Approved MEL KHACHATOURIAN
Smoke Detectors 5/6/2025 Approved MEL KHACHATOURIAN
Final 5/9/2025 OK to Issue CofO BOBBY KEY