2057 S PARNELL AVE 90025

Certificate Information: 2057 S PARNELL AVE 90025

Application / Permit
21016-10000-58556
Plan Check / Job No.
B21LA23582
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 3-CAR GARAGE TO DETACHED ADU PER STATE LAW (1-STORY)
Permit Issued
Issued on 5/31/2022
Issuing Office
Current Status
CofO Issued on 3/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2021 APPLICANT
Assigned to Plan Check Engineer 12/28/2021 CARLOS MONTES
Corrections Issued 12/29/2021 CARLOS MONTES
Applicant returned to address corrections 2/10/2022 CARLOS MONTES
Plan Check Approved 4/30/2022 CARLOS MONTES
Issued 5/31/2022 APPLICANT
CofO in Progress 3/15/2023 STEPHANIE SWANSON
Permit Finaled 3/21/2023 DANIEL ORRANTE
CofO Issued 3/21/2023 DANIEL ORRANTE
Permit Finaled 3/21/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/21/2022 JOSE HERNANDEZ
Sewer availability Cleared 2/21/2022 JOSE HERNANDEZ
Specific Plan Cleared 3/13/2022 EDUARDO HERMOSO
Eng Process Fee Ord 176,300 Cleared 4/26/2022 KATHLEEN LEE

Contact Information

Contractor Ariel Muller; Lic. No.: 1026822-B       ,
Engineer Keshishian,, Anthony; Lic. No.: C89551 2654 RISA D      GLENDALE, CA 91208

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/5/2022 Approved CLAYTON GRAHAM
Footing/Foundation/Slab 8/26/2022 Not Ready for Inspection STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 8/29/2022 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 8/31/2022 Corrections Issued STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 8/31/2022 Not Ready for Inspection STEPHANIE SWANSON
PLUMBING-Rough 8/31/2022 Corrections Issued STEPHANIE SWANSON
Wood Frame 8/31/2022 Not Ready for Inspection STEPHANIE SWANSON
ELECTRICAL-Rough 9/2/2022 Approved STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 9/2/2022 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 9/2/2022 Partial Approval STEPHANIE SWANSON
Special/Order Compliance 10/6/2022 Partial Inspection CLAYTON GRAHAM
Excavation/Setback/Form/Re-Bar 10/7/2022 Partial Approval STEPHANIE SWANSON
BUILDING-Rough-Frame 10/19/2022 Corrections Issued STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 10/19/2022 Approved STEPHANIE SWANSON
Wood Frame 10/21/2022 No Access for Inspection ANDREW NAVE
BUILDING-Rough-Frame 11/3/2022 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 11/3/2022 Approved STEPHANIE SWANSON
HVAC-Rough 11/3/2022 Approved STEPHANIE SWANSON
PLUMBING-Rough 11/3/2022 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 11/7/2022 Approved STEPHANIE SWANSON
Insulation 11/7/2022 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 11/17/2022 Approved STEPHANIE SWANSON
Green Building Rough 11/17/2022 Approved STEPHANIE SWANSON
Insulation 11/17/2022 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 11/17/2022 Partial Approval STEPHANIE SWANSON
METHANE-Rough 11/17/2022 Approved STEPHANIE SWANSON
PLUMBING-Rough 11/17/2022 Approved STEPHANIE SWANSON
Drywall Nailing 12/2/2022 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 12/19/2022 Approved STEPHANIE SWANSON
Shower Pan 12/19/2022 Approved STEPHANIE SWANSON
Final 2/6/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Green Building Final 2/6/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
SGSOV-Seismic Gas S/O Valve 2/6/2023 SGSOV Not Ready GERMAN RODRIGUEZ MENDOZA
Smoke Detectors 2/6/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Final 2/28/2023 No Access for Inspection CHRISTOPHER WILSON
Green Building Final 2/28/2023 No Access for Inspection CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 2/28/2023 SGSOV Not Ready CHRISTOPHER WILSON
Smoke Detectors 2/28/2023 No Access for Inspection CHRISTOPHER WILSON
ELECTRICAL-Final 3/1/2023 Corrections Issued STEPHANIE SWANSON
Final 3/1/2023 Corrections Issued STEPHANIE SWANSON
HVAC-Final 3/1/2023 Corrections Issued STEPHANIE SWANSON
PLUMBING-Final 3/1/2023 Corrections Issued STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 3/1/2023 SGSOV Not Ready STEPHANIE SWANSON
Smoke Detectors 3/1/2023 Approved STEPHANIE SWANSON
ELECTRICAL-Final 3/9/2023 Approved STEPHANIE SWANSON
Final 3/9/2023 Corrections Issued STEPHANIE SWANSON
Green Building Final 3/9/2023 Approved STEPHANIE SWANSON
HVAC-Final 3/9/2023 Approved STEPHANIE SWANSON
PLUMBING-Final 3/9/2023 Approved STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 3/9/2023 SGSOV Approved STEPHANIE SWANSON
Final 3/15/2023 OK to Issue CofO STEPHANIE SWANSON