2138 1/2 S SYCAMORE AVE 90016
Certificate Information: 2138 1/2 S SYCAMORE AVE 90016
- Application / Permit
- 21016-10000-58550
- Plan Check / Job No.
- B21LA23575
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: CONVERTING EXISTING GARAGE TO ADU WITH ADDITION
- Permit Issued
- Issued on 4/28/2022
- Issuing Office
- Current Status
- CofO Issued on 2/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2022 | ARSALAN SHABESTARI |
| Corrections Issued | 1/20/2022 | ARSALAN SHABESTARI |
| Quality Review Completed | 1/31/2022 | MICHAEL PEREZ |
| Applicant returned to address corrections | 4/7/2022 | ARSALAN SHABESTARI |
| Plan Check Approved | 4/13/2022 | ARSALAN SHABESTARI |
| Issued | 4/28/2022 | APPLICANT |
| CofO in Progress | 1/13/2023 | CALEB MEISTER |
| CofO in Progress | 1/13/2023 | CALEB MEISTER |
| CofO in Progress | 2/15/2023 | CALEB MEISTER |
| Permit Finaled | 2/19/2023 | DEROLD HAUFF |
| Permit Finaled | 2/19/2023 | DEROLD HAUFF |
| CofO Issued | 2/19/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/2/2022 | CELINA MORENO |
| Sewer availability | Cleared | 2/2/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2022 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hamilton,, John O; Lic. No.: NA53284 | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/6/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 7/27/2022 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2022 | Approved | STUART CHAPMAN |
| HVAC-Rough | 7/27/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 7/27/2022 | Approved | STUART CHAPMAN |
| Insulation | 8/2/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 8/2/2022 | Partial Approval | STUART CHAPMAN |
| Drywall Nailing | 8/16/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 8/16/2022 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 12/22/2022 | Not Ready for Inspection | CALEB MEISTER |
| Final | 12/22/2022 | Corrections Issued | CALEB MEISTER |
| Green Building Final | 12/22/2022 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Rough | 12/22/2022 | Not Ready for Inspection | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 12/22/2022 | SGSOV Not Ready | CALEB MEISTER |
| Smoke Detectors | 12/22/2022 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 1/6/2023 | Approved | CALEB MEISTER |
| Final | 1/6/2023 | Conditional Approval | CALEB MEISTER |
| Green Building Final | 1/6/2023 | Approved | CALEB MEISTER |
| Green Building Rough | 1/6/2023 | Approved | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 1/6/2023 | SGSOV Not Required | CALEB MEISTER |
| Smoke Detectors | 1/6/2023 | Approved | CALEB MEISTER |
| Final | 1/12/2023 | Not Ready for Inspection | CALEB MEISTER |