2138 1/2 S SYCAMORE AVE 90016

Certificate Information: 2138 1/2 S SYCAMORE AVE 90016

Application / Permit
21016-10000-58550
Plan Check / Job No.
B21LA23575
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: CONVERTING EXISTING GARAGE TO ADU WITH ADDITION
Permit Issued
Issued on 4/28/2022
Issuing Office
Current Status
CofO Issued on 2/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/17/2021 APPLICANT
Assigned to Plan Check Engineer 1/13/2022 ARSALAN SHABESTARI
Corrections Issued 1/20/2022 ARSALAN SHABESTARI
Quality Review Completed 1/31/2022 MICHAEL PEREZ
Applicant returned to address corrections 4/7/2022 ARSALAN SHABESTARI
Plan Check Approved 4/13/2022 ARSALAN SHABESTARI
Issued 4/28/2022 APPLICANT
CofO in Progress 1/13/2023 CALEB MEISTER
CofO in Progress 1/13/2023 CALEB MEISTER
CofO in Progress 2/15/2023 CALEB MEISTER
Permit Finaled 2/19/2023 DEROLD HAUFF
Permit Finaled 2/19/2023 DEROLD HAUFF
CofO Issued 2/19/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/2/2022 CELINA MORENO
Sewer availability Cleared 2/2/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 2/7/2022 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,
Engineer Hamilton,, John O; Lic. No.: NA53284       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/6/2022 Approved STUART CHAPMAN
ELECTRICAL-Rough 7/27/2022 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 7/27/2022 Approved STUART CHAPMAN
HVAC-Rough 7/27/2022 Approved STUART CHAPMAN
PLUMBING-Rough 7/27/2022 Approved STUART CHAPMAN
Insulation 8/2/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 8/2/2022 Partial Approval STUART CHAPMAN
Drywall Nailing 8/16/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 8/16/2022 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 12/22/2022 Not Ready for Inspection CALEB MEISTER
Final 12/22/2022 Corrections Issued CALEB MEISTER
Green Building Final 12/22/2022 Not Ready for Inspection CALEB MEISTER
Green Building Rough 12/22/2022 Not Ready for Inspection CALEB MEISTER
SGSOV-Seismic Gas S/O Valve 12/22/2022 SGSOV Not Ready CALEB MEISTER
Smoke Detectors 12/22/2022 Not Ready for Inspection CALEB MEISTER
BUILDING-Rough-Frame 1/6/2023 Approved CALEB MEISTER
Final 1/6/2023 Conditional Approval CALEB MEISTER
Green Building Final 1/6/2023 Approved CALEB MEISTER
Green Building Rough 1/6/2023 Approved CALEB MEISTER
SGSOV-Seismic Gas S/O Valve 1/6/2023 SGSOV Not Required CALEB MEISTER
Smoke Detectors 1/6/2023 Approved CALEB MEISTER
Final 1/12/2023 Not Ready for Inspection CALEB MEISTER