7516 S STEWART AVE 90045
Certificate Information: 7516 S STEWART AVE 90045
- Application / Permit
- 21016-10000-58535
- Plan Check / Job No.
- B21LA23562
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REAR ADDITION AND INTERIOR REMODEL TO (E) SFD
- Permit Issued
- Issued on 4/27/2022
- Issuing Office
- Current Status
- CofO Issued on 3/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/28/2021 | STANLEY RAAP |
| Corrections Issued | 1/4/2022 | STANLEY RAAP |
| Building Plans Picked Up | 1/10/2022 | APPLICANT |
| Applicant returned to address corrections | 3/17/2022 | FERNANDO FLORES |
| Plan Check Approved | 3/18/2022 | FERNANDO FLORES |
| Issued | 4/27/2022 | APPLICANT |
| CofO in Progress | 3/13/2023 | BOBBY KEY |
| Permit Finaled | 3/15/2023 | DANIEL ORRANTE |
| CofO Issued | 3/15/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/15/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/21/2022 | PATRICK MISCHLICH |
| Roof/Waste drainage to street | Cleared | 1/21/2022 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2022 | SAUL GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chavez,, Eduardo; Lic. No.: C76372 | 437 ARCADIA WAY WALNUT, CA 91789 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/27/2022 | Conditional Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 6/9/2022 | Approved | BOBBY KEY |
| Special/Order Compliance | 6/9/2022 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2022 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 6/30/2022 | Partial Approval | BOBBY KEY |
| Pre-Inspection | 7/6/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2022 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 10/4/2022 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 10/4/2022 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 10/4/2022 | Conditional Approval | BOBBY KEY |
| Special/Order Compliance | 10/4/2022 | Partial Inspection | CLAYTON GRAHAM |
| Wood Frame | 10/4/2022 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 10/11/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 10/11/2022 | Approved | BOBBY KEY |
| Green Building Rough | 10/24/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 10/24/2022 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 10/31/2022 | Approved | BOBBY KEY |
| Insulation | 10/31/2022 | Approved | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 10/31/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 11/10/2022 | Approved | BOBBY KEY |
| Final | 11/10/2022 | Corrections Issued | BOBBY KEY |
| Shower Pan | 11/10/2022 | Approved | BOBBY KEY |
| HVAC-Final | 2/16/2023 | Partial Approval | BOBBY KEY |
| Service/Power Release | 2/16/2023 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Final | 2/27/2023 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 3/1/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 3/1/2023 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 3/8/2023 | Approved | BOBBY KEY |
| HVAC-Final | 3/8/2023 | Corrections Issued | BOBBY KEY |
| Service/Power Release | 3/8/2023 | Approved | BOBBY KEY |
| Final | 3/13/2023 | OK to Issue CofO | BOBBY KEY |
| Green Building Final | 3/13/2023 | Approved | BOBBY KEY |
| HVAC-Final | 3/13/2023 | Approved | BOBBY KEY |
| PLUMBING-Final | 3/13/2023 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 3/13/2023 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 3/13/2023 | Approved | BOBBY KEY |