8005 S GONZAGA AVE 90045
Certificate Information: 8005 S GONZAGA AVE 90045
- Application / Permit
- 21016-10000-58493
- Plan Check / Job No.
- B21LA23531
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL OF 2ND FLOOR MASTER BATHROOM, WIC. CREATE (N) BATHROOM IN 2ND FLOOR (NO ADDITION)
- Permit Issued
- Issued on 3/16/2022
- Issuing Office
- Current Status
- Permit Finaled on 5/27/2022
Permit Application Status History
| Submitted | 12/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2021 | KHUONG TRUONG |
| Corrections Issued | 12/26/2021 | KHUONG TRUONG |
| Plan Check Approved | 1/19/2022 | JOSEPH RAFOLS |
| Issued | 3/16/2022 | APPLICANT |
| Building Plans Picked Up | 3/22/2022 | APPLICANT |
| Permit Finaled | 5/26/2022 | BOBBY KEY |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Glew Build; Lic. No.: 944892-B | 342 AVENUE E REDONDO BEACH, CA 90277 |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 3/18/2022 | Corrections Issued | BOBBY KEY |
| Pre-Inspection | 3/18/2022 | Partial Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 3/22/2022 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Rough | 3/22/2022 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Rough | 3/22/2022 | Not Ready for Inspection | BOBBY KEY |
| Insulation | 3/22/2022 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 3/22/2022 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 3/23/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 3/23/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 3/23/2022 | Approved | BOBBY KEY |
| Insulation | 3/23/2022 | Approved | BOBBY KEY |
| PLUMBING-Rough | 3/23/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 4/5/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 4/5/2022 | Partial Approval | RYAN SALAZAR |
| Shower Pan | 4/5/2022 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Final | 5/26/2022 | Approved | BOBBY KEY |
| Final | 5/26/2022 | Permit Finaled | BOBBY KEY |
| PLUMBING-Final | 5/26/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 5/26/2022 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 5/26/2022 | Approved | BOBBY KEY |