6220 W SELMA AVE 90028

Certificate Information: 6220 W SELMA AVE 90028

Application / Permit
21016-10000-58474
Plan Check / Job No.
B21LA23513
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
TENANT IMPROVEMENT OF INTERIOR PARTITION, SUSPENDED CEILING, INTERIOR FINISH, KITCHENS AND RELATED SERVICE AREAS OF THE MARKET.
Permit Issued
Issued on 1/7/2025
Issuing Office
Current Status
Permit Finaled on 4/14/2026

Permit Application Status History

Submitted 12/17/2021 APPLICANT
Assigned to Plan Check Engineer 12/17/2021 JOE VO
Corrections Issued 12/18/2021 JOE VO
Applicant returned to address corrections 12/20/2021 JOE VO
Disabled Access Plans Picked Up 1/11/2022 APPLICANT
Plan Check Approved 1/5/2025 JOE VO
Issued 1/7/2025 APPLICANT
Permit Finaled 4/3/2026 DAVID BURKHEAD

Permit Application Clearance Information

Green Code Cleared 1/13/2024 JOE VO
Food Service Establishment Cleared 10/8/2024 CRYSTOL BRANDT
Food establishment approval Cleared 12/23/2024 LACDHS APPROVED
DAS Clearance Cleared 12/27/2024 CAROLYNN NEPOMUCENO

Contact Information

Architect Williams,, Bradley James; Lic. No.: C30604 3091 ARMOURDALE AVENUE      LONG BEACH, CA 90808
Contractor Rsvc Company; Lic. No.: 961558-B       ,

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/2/2025 Not Ready for Inspection TIMOTHY POWELL
Structural Steel Frame 4/10/2025 Not Ready for Inspection TIMOTHY POWELL
Excavation/Setback/Form/Re-Bar 4/14/2025 Not Ready for Inspection TIMOTHY POWELL
Excavation/Setback/Form/Re-Bar 4/16/2025 Not Ready for Inspection TIMOTHY POWELL
Excavation/Setback/Form/Re-Bar 4/24/2025 Not Ready for Inspection CHRISTOPHER BLACKWOOD
Footing/Foundation/Slab 4/28/2025 Partial Approval RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 5/7/2025 Partial Approval TIMOTHY POWELL
Light Gage Steel Frame 5/7/2025 Partial Inspection TIMOTHY POWELL
Special/Order Compliance 6/4/2025 Partial Inspection TIMOTHY POWELL
Drywall Nailing 6/10/2025 No Access for Inspection MARTIN TAVITIAN
Excavation/Setback/Form/Re-Bar 6/11/2025 Partial Approval LUIS CCAMACHO
Drywall Nailing 6/12/2025 Partial Approval MARTIN TAVITIAN
Light Gage Steel Frame 6/12/2025 Partial Approval MARTIN TAVITIAN
Excavation/Setback/Form/Re-Bar 6/18/2025 Not Ready for Inspection CHRISTOPHER BLACKWOOD
Light Gage Steel Frame 6/18/2025 Partial Approval CHRISTOPHER BLACKWOOD
Drywall Nailing 6/20/2025 Not Ready for Inspection TIMOTHY POWELL
Excavation/Setback/Form/Re-Bar 6/20/2025 Partial Approval TIMOTHY POWELL
Light Gage Steel Frame 6/23/2025 Partial Approval TIMOTHY POWELL
Drywall Nailing 7/7/2025 Partial Approval CHRISTOPHER BLACKWOOD
Excavation/Setback/Form/Re-Bar 7/7/2025 Partial Approval CHRISTOPHER BLACKWOOD
Drywall Nailing 7/10/2025 Partial Approval TIMOTHY POWELL
Excavation/Setback/Form/Re-Bar 7/10/2025 Partial Approval TIMOTHY POWELL
Light Gage Steel Frame 7/10/2025 Not Ready for Inspection TIMOTHY POWELL
Drywall Nailing 7/11/2025 Not Ready for Inspection PAUL BAZERKANIAN
Light Gage Steel Frame 7/11/2025 Not Ready for Inspection PAUL BAZERKANIAN
Drywall Nailing 7/23/2025 Partial Approval TIMOTHY POWELL
Excavation/Setback/Form/Re-Bar 7/23/2025 Partial Inspection TIMOTHY POWELL
Light Gage Steel Frame 7/23/2025 Not Ready for Inspection TIMOTHY POWELL
Drywall Nailing 7/31/2025 Not Ready for Inspection TIMOTHY POWELL
Drywall Nailing 8/12/2025 Not Ready for Inspection TIMOTHY POWELL
Insulation 8/12/2025 Partial Approval TIMOTHY POWELL
Light Gage Steel Frame 8/12/2025 Not Ready for Inspection TIMOTHY POWELL
T-Bar Ceiling 8/26/2025 Not Ready for Inspection JEROME BLACKWOOD
T-Bar Ceiling 9/4/2025 Not Ready for Inspection CHRISTOPHER BLACKWOOD
T-Bar Ceiling 9/5/2025 Off-Hour Fees Due
T-Bar Ceiling 9/8/2025 Partial Approval TIMOTHY POWELL
Special/Order Compliance 9/30/2025 Not Ready for Inspection LUIS CCAMACHO
Special/Order Compliance 10/3/2025 Partial Approval TIMOTHY POWELL
Pre-Inspection 12/8/2025 Partial Inspection DAVID BURKHEAD
Pre-Inspection 2/2/2026 Partial Inspection DAVID BURKHEAD
Special/Order Compliance 2/6/2026 Corrections Issued DAVID BURKHEAD
Special/Order Compliance 2/11/2026 Corrections Issued DAVID BURKHEAD
Drywall Nailing 2/25/2026 Partial Approval LUIS CCAMACHO
Final 3/12/2026 Not Ready for Inspection LUIS CCAMACHO
Green Building Final 3/12/2026 Not Ready for Inspection LUIS CCAMACHO
SGSOV-Seismic Gas S/O Valve 3/12/2026 SGSOV Approved LUIS CCAMACHO
Smoke Detectors 3/12/2026 Approved LUIS CCAMACHO
Final 3/24/2026 Partial Inspection LUIS CCAMACHO
Green Building Final 3/24/2026 Approved LUIS CCAMACHO
Final 4/3/2026 Permit Finaled DAVID BURKHEAD