5836 1/2 S 8TH AVE 90043
Certificate Information: 5836 1/2 S 8TH AVE 90043
- Application / Permit
- 21016-10000-58465
- Plan Check / Job No.
- B21LA23501
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* CONVERT (E) 1-STORY DETACHED 2-CAR GARAGE TO ADU PER CA GC 65852.2(e)(1)(A).
- Permit Issued
- Issued on 5/27/2022
- Issuing Office
- Current Status
- CofO Issued on 5/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/24/2022 | VIVIAN LAO |
| Corrections Issued | 1/25/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 5/17/2022 | VIVIAN LAO |
| Plan Check Approved | 5/19/2022 | VIVIAN LAO |
| Issued | 5/27/2022 | APPLICANT |
| CofO in Progress | 5/7/2024 | JOSE MACIAS |
| CofO in Progress | 5/7/2024 | JOSE MACIAS |
| Permit Finaled | 5/17/2024 | DEROLD HAUFF |
| CofO Issued | 5/17/2024 | DEROLD HAUFF |
| Permit Finaled | 5/17/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/16/2022 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 3/16/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 3/16/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 3/23/2022 | STEVE MELGAR |
| Construction within easement | Cleared | 4/23/2022 | RIDWAN HARDY |
| Tenant Habitability Plan | Cleared | 5/12/2022 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | , ; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/10/2023 | Corrections Issued | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 4/18/2023 | Approved | ENRIQUE MIRELES |
| Sewer | 4/18/2023 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 4/18/2023 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 4/24/2023 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 4/24/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2023 | Corrections Issued | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2023 | Corrections Issued | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 6/21/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 6/21/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2023 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 6/21/2023 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 6/21/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 6/21/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 7/18/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 8/1/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 8/11/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 12/12/2023 | SGSOV Not Ready | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 12/21/2023 | SGSOV Not Ready | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 12/28/2023 | SGSOV Not Ready | ENRIQUE MIRELES |
| Final | 1/4/2024 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 1/4/2024 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 1/4/2024 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 1/4/2024 | Approved | ENRIQUE MIRELES |
| Final | 2/14/2024 | Corrections Issued | JOSE MACIAS |
| Final | 2/27/2024 | Corrections Issued | JOSE MACIAS |
| HVAC-Final | 2/27/2024 | Approved | JOSE MACIAS |
| PLUMBING-Final | 2/27/2024 | Approved | JOSE MACIAS |
| Final | 3/15/2024 | OK to Issue CofO | JOSE MACIAS |
| Final | 5/7/2024 | OK to Issue CofO | JOSE MACIAS |