5836 1/2 S 8TH AVE 90043

Certificate Information: 5836 1/2 S 8TH AVE 90043

Application / Permit
21016-10000-58465
Plan Check / Job No.
B21LA23501
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* CONVERT (E) 1-STORY DETACHED 2-CAR GARAGE TO ADU PER CA GC 65852.2(e)(1)(A).
Permit Issued
Issued on 5/27/2022
Issuing Office
Current Status
CofO Issued on 5/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/24/2022 APPLICANT
Assigned to Plan Check Engineer 1/24/2022 VIVIAN LAO
Corrections Issued 1/25/2022 VIVIAN LAO
Applicant returned to address corrections 5/17/2022 VIVIAN LAO
Plan Check Approved 5/19/2022 VIVIAN LAO
Issued 5/27/2022 APPLICANT
CofO in Progress 5/7/2024 JOSE MACIAS
CofO in Progress 5/7/2024 JOSE MACIAS
Permit Finaled 5/17/2024 DEROLD HAUFF
CofO Issued 5/17/2024 DEROLD HAUFF
Permit Finaled 5/17/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/16/2022 STEVE MELGAR
Roof/Waste drainage to street Cleared 3/16/2022 STEVE MELGAR
Sewer availability Cleared 3/16/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 3/23/2022 STEVE MELGAR
Construction within easement Cleared 4/23/2022 RIDWAN HARDY
Tenant Habitability Plan Cleared 5/12/2022 ISMAEL HERNANDEZ

Contact Information

Contractor Owner-Builder       ,
Engineer , ; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/10/2023 Corrections Issued ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 4/18/2023 Approved ENRIQUE MIRELES
Sewer 4/18/2023 Approved ENRIQUE MIRELES
Underground Mechanical 4/18/2023 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 4/24/2023 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 4/24/2023 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 6/8/2023 Corrections Issued ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 6/14/2023 Corrections Issued ENRIQUE MIRELES
BUILDING-Rough-Frame 6/21/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 6/21/2023 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 6/21/2023 Approved ENRIQUE MIRELES
Green Building Rough 6/21/2023 Approved ENRIQUE MIRELES
HVAC-Rough 6/21/2023 Approved ENRIQUE MIRELES
PLUMBING-Rough 6/21/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 7/18/2023 Approved ENRIQUE MIRELES
Insulation 8/1/2023 Approved ENRIQUE MIRELES
Drywall Nailing 8/11/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 12/12/2023 SGSOV Not Ready ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 12/21/2023 SGSOV Not Ready ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 12/28/2023 SGSOV Not Ready ENRIQUE MIRELES
Final 1/4/2024 Corrections Issued ENRIQUE MIRELES
Green Building Final 1/4/2024 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 1/4/2024 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 1/4/2024 Approved ENRIQUE MIRELES
Final 2/14/2024 Corrections Issued JOSE MACIAS
Final 2/27/2024 Corrections Issued JOSE MACIAS
HVAC-Final 2/27/2024 Approved JOSE MACIAS
PLUMBING-Final 2/27/2024 Approved JOSE MACIAS
Final 3/15/2024 OK to Issue CofO JOSE MACIAS
Final 5/7/2024 OK to Issue CofO JOSE MACIAS