1031 1/2 W GAGE AVE 90044

Certificate Information: 1031 1/2 W GAGE AVE 90044

Application / Permit
21016-10000-58462
Plan Check / Job No.
B21LA23499
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) one-story, three-car garage to Accessory Dwelling Unit per GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 3/2/2022
Issuing Office
Current Status
CofO Issued on 10/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/16/2021 APPLICANT
Assigned to Plan Check Engineer 12/22/2021 MINA HABILI
Corrections Issued 12/27/2021 MINA HABILI
Plan Check Approved 2/17/2022 SHANGQIN XIE
Issued 3/2/2022 APPLICANT
Building Plans Picked Up 3/8/2022 APPLICANT
CofO in Progress 9/30/2024 CRAIG DAVIS
Permit Finaled 10/1/2024 RUBEN SALAS
CofO Issued 10/1/2024 RUBEN SALAS
Permit Finaled 10/1/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/3/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 1/3/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 1/5/2022 CHRISTOPHER ROCHA
Tenant Habitability Plan Cleared 1/5/2022 MICHAEL SOTO

Contact Information

Contractor Jerahian Araz; Lic. No.: 1045340-B 250 N COLLEGE PARK DR F36      UPLAND, CA 91786

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/11/2023 No Access for Inspection CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 10/12/2023 Corrections Issued CRAIG DAVIS
Footing/Foundation/Slab 10/12/2023 Corrections Issued CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 10/13/2023 Not Ready for Inspection CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 10/18/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 10/18/2023 Corrections Issued MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 10/25/2023 Corrections Issued RONNIE MINDANAO
Footing/Foundation/Slab 10/25/2023 Not Ready for Inspection RONNIE MINDANAO
Footing/Foundation/Slab 10/27/2023 Approved CRAIG DAVIS
BUILDING-Rough-Frame 11/14/2023 Not Ready for Inspection CRAIG DAVIS
PLUMBING-Rough 11/14/2023 Partial Approval CRAIG DAVIS
Underground Mechanical 11/14/2023 Not Ready for Inspection CRAIG DAVIS
Wood Frame 11/14/2023 Not Ready for Inspection CRAIG DAVIS
BUILDING-Rough-Frame 11/20/2023 Not Ready for Inspection RONNIE MINDANAO
ELECTRICAL-Rough 11/20/2023 Approved RONNIE MINDANAO
HVAC-Rough 11/20/2023 Not Ready for Inspection RONNIE MINDANAO
Wood Frame 11/20/2023 Not Ready for Inspection RONNIE MINDANAO
BUILDING-Rough-Frame 12/1/2023 Not Ready for Inspection CRAIG DAVIS
Gas Test 12/1/2023 Approved CRAIG DAVIS
PLUMBING-Rough 12/1/2023 Approved CRAIG DAVIS
BUILDING-Rough-Frame 12/18/2023 Approved CRAIG DAVIS
Interior/Exterior Lathing 12/18/2023 Approved CRAIG DAVIS
Wood Frame 12/18/2023 Approved CRAIG DAVIS
Insulation 12/26/2023 Partial Approval CRAIG DAVIS
Drywall Nailing 1/19/2024 Corrections Issued RONNIE MINDANAO
Drywall Nailing 1/24/2024 Approved RONNIE MINDANAO
Insulation 1/24/2024 Approved RONNIE MINDANAO
Interior/Exterior Lathing 3/4/2024 Not Ready for Inspection RONNIE MINDANAO
Interior/Exterior Lathing 3/5/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 3/20/2024 Corrections Issued CRAIG DAVIS
Final 3/20/2024 Corrections Issued CRAIG DAVIS
HVAC-Final 3/20/2024 Corrections Issued CRAIG DAVIS
PLUMBING-Final 3/20/2024 Corrections Issued CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 3/20/2024 SGSOV Not Ready CRAIG DAVIS
Smoke Detectors 3/20/2024 Approved CRAIG DAVIS
ELECTRICAL-Final 3/29/2024 Partial Approval CRAIG DAVIS
Final 3/29/2024 Not Ready for Inspection CRAIG DAVIS
PLUMBING-Final 3/29/2024 Partial Inspection CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 3/29/2024 SGSOV Not Ready CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 4/17/2024 SGSOV Not Ready CRAIG DAVIS
ELECTRICAL-Final 4/25/2024 Corrections Issued JOSE MACIAS
Final 4/25/2024 Corrections Issued JOSE MACIAS
Gas Test 4/25/2024 Approved JOSE MACIAS
PLUMBING-Final 4/25/2024 Approved JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 4/25/2024 SGSOV Not Ready JOSE MACIAS
Final 5/2/2024 Not Ready for Inspection CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 5/2/2024 SGSOV Not Ready CRAIG DAVIS
Final 5/10/2024 Not Ready for Inspection CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 5/10/2024 SGSOV Not Ready CRAIG DAVIS
ELECTRICAL-Final 9/3/2024 Corrections Issued CRAIG DAVIS
Final 9/3/2024 Not Ready for Inspection CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 9/3/2024 SGSOV Approved CRAIG DAVIS
ELECTRICAL-Final 9/27/2024 Approved CRAIG DAVIS
Final 9/27/2024 OK to Issue CofO CRAIG DAVIS
HVAC-Final 9/27/2024 Approved CRAIG DAVIS
PLUMBING-Final 9/27/2024 Approved CRAIG DAVIS
Service/Power Release 9/27/2024 Approved CRAIG DAVIS