1031 1/2 W GAGE AVE 90044
Certificate Information: 1031 1/2 W GAGE AVE 90044
- Application / Permit
- 21016-10000-58462
- Plan Check / Job No.
- B21LA23499
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) one-story, three-car garage to Accessory Dwelling Unit per GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 3/2/2022
- Issuing Office
- Current Status
- CofO Issued on 10/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2021 | MINA HABILI |
| Corrections Issued | 12/27/2021 | MINA HABILI |
| Plan Check Approved | 2/17/2022 | SHANGQIN XIE |
| Issued | 3/2/2022 | APPLICANT |
| Building Plans Picked Up | 3/8/2022 | APPLICANT |
| CofO in Progress | 9/30/2024 | CRAIG DAVIS |
| Permit Finaled | 10/1/2024 | RUBEN SALAS |
| CofO Issued | 10/1/2024 | RUBEN SALAS |
| Permit Finaled | 10/1/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/3/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 1/3/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 1/5/2022 | CHRISTOPHER ROCHA |
| Tenant Habitability Plan | Cleared | 1/5/2022 | MICHAEL SOTO |
Contact Information
| Contractor | Jerahian Araz; Lic. No.: 1045340-B | 250 N COLLEGE PARK DR F36 UPLAND, CA 91786 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/11/2023 | No Access for Inspection | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 10/12/2023 | Corrections Issued | CRAIG DAVIS |
| Footing/Foundation/Slab | 10/12/2023 | Corrections Issued | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 10/13/2023 | Not Ready for Inspection | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 10/18/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 10/18/2023 | Corrections Issued | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 10/25/2023 | Corrections Issued | RONNIE MINDANAO |
| Footing/Foundation/Slab | 10/25/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Footing/Foundation/Slab | 10/27/2023 | Approved | CRAIG DAVIS |
| BUILDING-Rough-Frame | 11/14/2023 | Not Ready for Inspection | CRAIG DAVIS |
| PLUMBING-Rough | 11/14/2023 | Partial Approval | CRAIG DAVIS |
| Underground Mechanical | 11/14/2023 | Not Ready for Inspection | CRAIG DAVIS |
| Wood Frame | 11/14/2023 | Not Ready for Inspection | CRAIG DAVIS |
| BUILDING-Rough-Frame | 11/20/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Rough | 11/20/2023 | Approved | RONNIE MINDANAO |
| HVAC-Rough | 11/20/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Wood Frame | 11/20/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 12/1/2023 | Not Ready for Inspection | CRAIG DAVIS |
| Gas Test | 12/1/2023 | Approved | CRAIG DAVIS |
| PLUMBING-Rough | 12/1/2023 | Approved | CRAIG DAVIS |
| BUILDING-Rough-Frame | 12/18/2023 | Approved | CRAIG DAVIS |
| Interior/Exterior Lathing | 12/18/2023 | Approved | CRAIG DAVIS |
| Wood Frame | 12/18/2023 | Approved | CRAIG DAVIS |
| Insulation | 12/26/2023 | Partial Approval | CRAIG DAVIS |
| Drywall Nailing | 1/19/2024 | Corrections Issued | RONNIE MINDANAO |
| Drywall Nailing | 1/24/2024 | Approved | RONNIE MINDANAO |
| Insulation | 1/24/2024 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 3/4/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Interior/Exterior Lathing | 3/5/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 3/20/2024 | Corrections Issued | CRAIG DAVIS |
| Final | 3/20/2024 | Corrections Issued | CRAIG DAVIS |
| HVAC-Final | 3/20/2024 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Final | 3/20/2024 | Corrections Issued | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 3/20/2024 | SGSOV Not Ready | CRAIG DAVIS |
| Smoke Detectors | 3/20/2024 | Approved | CRAIG DAVIS |
| ELECTRICAL-Final | 3/29/2024 | Partial Approval | CRAIG DAVIS |
| Final | 3/29/2024 | Not Ready for Inspection | CRAIG DAVIS |
| PLUMBING-Final | 3/29/2024 | Partial Inspection | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 3/29/2024 | SGSOV Not Ready | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 4/17/2024 | SGSOV Not Ready | CRAIG DAVIS |
| ELECTRICAL-Final | 4/25/2024 | Corrections Issued | JOSE MACIAS |
| Final | 4/25/2024 | Corrections Issued | JOSE MACIAS |
| Gas Test | 4/25/2024 | Approved | JOSE MACIAS |
| PLUMBING-Final | 4/25/2024 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 4/25/2024 | SGSOV Not Ready | JOSE MACIAS |
| Final | 5/2/2024 | Not Ready for Inspection | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 5/2/2024 | SGSOV Not Ready | CRAIG DAVIS |
| Final | 5/10/2024 | Not Ready for Inspection | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 5/10/2024 | SGSOV Not Ready | CRAIG DAVIS |
| ELECTRICAL-Final | 9/3/2024 | Corrections Issued | CRAIG DAVIS |
| Final | 9/3/2024 | Not Ready for Inspection | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 9/3/2024 | SGSOV Approved | CRAIG DAVIS |
| ELECTRICAL-Final | 9/27/2024 | Approved | CRAIG DAVIS |
| Final | 9/27/2024 | OK to Issue CofO | CRAIG DAVIS |
| HVAC-Final | 9/27/2024 | Approved | CRAIG DAVIS |
| PLUMBING-Final | 9/27/2024 | Approved | CRAIG DAVIS |
| Service/Power Release | 9/27/2024 | Approved | CRAIG DAVIS |