1550 S STADIUM WAY 90012

Certificate Information: 1550 S STADIUM WAY 90012

Application / Permit
21016-10000-58444
Plan Check / Job No.
B21LA23491
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(35) Condo-Multi Family
Work Description
Soft Story retrofit per LAMC DIV. 93. Install one ordinary steel moment frame for a condominium BLDG.
Permit Issued
Issued on 7/7/2022
Issuing Office
Metro
Current Status
CofC Issued on 10/13/2022

Permit Application Status History

Submitted 12/16/2021 APPLICANT
Assigned to Plan Check Engineer 1/6/2022 VARAND SARKISIAN
Corrections Issued 1/10/2022 VARAND SARKISIAN
Quality Review Completed 1/11/2022 HANS SANTIAGO
Building Plans Picked Up 1/14/2022 APPLICANT
Applicant returned to address corrections 3/23/2022 VARAND SARKISIAN
Plan Check Approved 6/27/2022 VARAND SARKISIAN
Issued 7/7/2022 APPLICANT
OK for CofC 9/1/2022 DARRYL ARNOLD
CofC Issued 10/13/2022 WINSTON DUNNING

Permit Application Clearance Information

Historic Resource Verification Cleared 3/24/2022 MAX LODER
Redevelopment Project Area Cleared 3/24/2022 SUSAN WONG
Abandoned oil well Cleared 6/21/2022 JOHN CONNEALLY
Tenant Habitability Plan Cleared 6/27/2022 RICARDO BOHORQUEZ

Contact Information

Contractor Core Contractors Llc; Lic. No.: 1038618-B 9800D TOPANGA CANYON BLVD   SUITE 324    CHATSWORTH, CA 91311
Engineer Deihimi,, Amir Hossein; Lic. No.: C78194 23172 PLAZA POINTE DR STE 145      LAGUNA HILLS, CA 92653

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/9/2022 Conditional Approval BRUCE CAMPBELL
Deputy Steel/Welding 8/17/2022 Conditional Approval BRUCE CAMPBELL
Deputy Drilled-In Anchors 8/18/2022 Conditional Approval MARK FERRARI
Excavation/Setback/Form/Re-Bar 8/19/2022 Approved BRUCE CAMPBELL
Footing/Foundation/Slab 8/19/2022 Approved BRUCE CAMPBELL
Structural Steel Frame 8/19/2022 Approved BRUCE CAMPBELL
Interior/Exterior Lathing 8/26/2022 Conditional Approval DARRYL ARNOLD
Interior/Exterior Lathing 8/29/2022 Conditional Approval DARRYL ARNOLD
Final 9/1/2022 Partial Inspection DARRYL ARNOLD
METHANE-Final 9/1/2022 Approved DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 9/1/2022 SGSOV Approved DARRYL ARNOLD
Smoke Detectors 9/1/2022 Approved DARRYL ARNOLD