6155 W PACKARD ST 90035

Certificate Information: 6155 W PACKARD ST 90035

Application / Permit
21016-10000-58262
Plan Check / Job No.
B21LA23433
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. Convert existing detached garage into an ADU per ordinance. COMPLY WITH DEPARTMENT ORDER effective date 05/30/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE ***SEE COMMENTS***
Permit Issued
Issued on 12/8/2022
Issuing Office
Current Status
CofO Issued on 9/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2021 APPLICANT
Assigned to Plan Check Engineer 12/20/2021 MICHAEL LOPEZ
Corrections Issued 12/20/2021 MICHAEL LOPEZ
Applicant returned to address corrections 8/9/2022 MICHAEL LOPEZ
Applicant returned to address corrections 9/9/2022 MICHAEL LOPEZ
Applicant returned to address corrections 9/13/2022 MICHAEL LOPEZ
Plan Check Approved 11/2/2022 KEVIN MORALES
Issued 12/8/2022 APPLICANT
CofO in Progress 7/30/2024 ROBERT NILES
CofO in Progress 8/22/2024 ROBERT CHAVEZ
CofO in Progress 8/22/2024 ROBERT CHAVEZ
CofO in Progress 8/22/2024 ROBERT CHAVEZ
Permit Finaled 9/6/2024 DANIEL SANCHEZ
CofO Issued 9/6/2024 DANIEL SANCHEZ
Permit Finaled 9/6/2024 DANIEL SANCHEZ

Permit Application Clearance Information

CPC Cleared 12/22/2021 RICHARD REASER
CPC Cleared 12/22/2021 RICHARD REASER
ZA Case Cleared 12/22/2021 RICHARD REASER
Address approval Cleared 12/23/2021 CINDY QI
Sewer availability Cleared 12/23/2021 CINDY QI
Eng Process Fee Ord 176,300 Cleared 1/5/2022 CINDY QI
HPOZ Cleared 7/20/2022 JONATHAN KAPLAN

Contact Information

Contractor Bella Development Llc; Lic. No.: 1081661-B       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/21/2022 Approved HAGOP BADOSSIAN
Deputy Drilled-In Anchors 1/12/2023 Approved JOHN TCHANG
Footing/Foundation/Slab 1/13/2023 Approved JOHN TCHANG
ELECTRICAL-Rough 1/24/2023 Partial Approval JOHN TCHANG
PLUMBING-Rough 1/24/2023 Approved JOHN TCHANG
Wood Frame 1/24/2023 Partial Approval JOHN TCHANG
Wood Frame 2/6/2023 Corrections Issued JOHN TCHANG
Drywall Nailing 2/28/2023 Approved JOHN TCHANG
Interior/Exterior Lathing 2/28/2023 Approved JOHN TCHANG
Interior/Exterior Lathing 4/11/2023 Approved PETER RUBIO
Shower Pan 4/11/2023 Not Ready for Inspection PETER RUBIO
Interior/Exterior Lathing 4/13/2023 Approved PETER RUBIO
Shower Pan 4/13/2023 Approved PETER RUBIO
Footing/Foundation/Slab 5/25/2023 Approved JOHN TCHANG
PLUMBING-Rough 5/25/2023 Approved JOHN TCHANG
BUILDING-Rough-Frame 9/27/2023 Approved PETER RUBIO
Final 9/27/2023 Corrections Issued PETER RUBIO
Green Building Final 9/27/2023 Corrections Issued PETER RUBIO
Green Building Rough 9/27/2023 Approved PETER RUBIO
METHANE-Final 9/27/2023 Approved PETER RUBIO
METHANE-Rough 9/27/2023 Approved PETER RUBIO
SGSOV-Seismic Gas S/O Valve 9/27/2023 SGSOV Approved PETER RUBIO
Smoke Detectors 9/27/2023 Approved PETER RUBIO
Final 10/10/2023 Corrections Issued ROBERT NILES
Green Building Final 10/10/2023 Partial Approval ROBERT NILES
Final 10/18/2023 Corrections Issued ROBERT NILES
Green Building Final 10/18/2023 Approved ROBERT NILES
Service/Power Release 1/16/2024 Not Ready for Inspection ROBERT NILES
Service/Power Release 3/19/2024 Approved ROBERT NILES
Final 7/30/2024 OK to Issue CofO ROBERT NILES