326 W GAGE AVE 90003
Certificate Information: 326 W GAGE AVE 90003
- Application / Permit
- 21016-10000-58233
- Plan Check / Job No.
- B21LA23418
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (E) BATH AT 2ND FLOOR TO BE REMODELED, NEW EGRESS WINDOWS AT (E) 1ST FLOOR BEDROOMS, (E) EXTERIOR SIDING TO BE REMOVED AND APPLY (N) STUCCO TO **WHOLE HOUSE** EXTERIOR WALLS.
- Permit Issued
- Issued on 3/18/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 5/16/2022
Permit Application Status History
| Submitted | 12/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2021 | DANIEL SANJUAN |
| Corrections Issued | 12/17/2021 | DANIEL SANJUAN |
| Applicant returned to address corrections | 2/3/2022 | KHUONG TRUONG |
| Applicant returned to address corrections | 2/26/2022 | ADAM HEGAZI |
| Plan Check Approved | 3/1/2022 | ADAM HEGAZI |
| Issued | 3/18/2022 | APPLICANT |
| Building Plans Picked Up | 3/21/2022 | APPLICANT |
| Permit Finaled | 5/13/2022 | MARIO CUEVAS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEREMY TODD, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARVIN FONSECA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GUEVARA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/25/2022 | Not Ready for Inspection | HORACE FULTZ |
| Pre-Inspection | 3/29/2022 | Approved | MARIO CUEVAS |
| ELECTRICAL-Rough | 4/26/2022 | Corrections Issued | MARIO CUEVAS |
| HVAC-Rough | 4/26/2022 | Corrections Issued | MARIO CUEVAS |
| Interior/Exterior Lathing | 4/26/2022 | Approved | MARIO CUEVAS |
| Special/Order Compliance | 4/26/2022 | Approved | MARIO CUEVAS |
| BUILDING-Rough-Frame | 5/10/2022 | Approved | MARIO CUEVAS |
| MERV13>=Final | 5/10/2022 | Approved | MARIO CUEVAS |
| Final | 5/13/2022 | Permit Finaled | MARIO CUEVAS |
| SGSOV-Seismic Gas S/O Valve | 5/13/2022 | SGSOV Approved | MARIO CUEVAS |
| Smoke Detectors | 5/13/2022 | Approved | MARIO CUEVAS |