800-810 S PACIFIC AVE 90731

Certificate Information: 800-810 S PACIFIC AVE 90731

Application / Permit
21016-10000-57905
Plan Check / Job No.
B21LA23286
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(27) Artist-in-Residence
Work Description
CHANGE OF USE FROM RETAIL TO MEDICAL OFFICE WITH INTERIOR REMODEL, NEW PARTITION WALLS AND CEILING. NO EXTERIOR WORL. ( 4020 SQ.FT., TENANT IMPROVEMENT OF GROUND FLOOR)(URM building .Impact tools shall not be used) "COMPLY WITH DEPARTMENT ORDER effective date 07/18/2014. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 5/3/2022
Issuing Office
Current Status
CofO Issued on 11/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/13/2022 APPLICANT
Assigned to Plan Check Engineer 1/20/2022 FARSHAD ALIMOHAMADI
Corrections Issued 1/25/2022 FARSHAD ALIMOHAMADI
Quality Review Completed 1/28/2022 SAI KHUM
Building Plans Picked Up 2/2/2022 APPLICANT
Green Plans Picked Up 2/11/2022 APPLICANT
Disabled Access Plans Picked Up 2/24/2022 APPLICANT
Applicant returned to address corrections 3/24/2022 FARSHAD ALIMOHAMADI
Plan Check Approved 4/28/2022 FARSHAD ALIMOHAMADI
Issued 5/3/2022 APPLICANT
CofO in Progress 11/15/2022 JOEY BUCHANAN
Permit Finaled 11/17/2022 DAVID TSAU
CofO Issued 11/17/2022 DAVID TSAU
Permit Finaled 11/17/2022 DAVID TSAU

Permit Application Clearance Information

"D" conditions Cleared 2/23/2022 ANACANY HURTADO
Metro Rail approval Cleared 3/3/2022 FARSHAD ALIMOHAMADI
Sewer availability Cleared 3/7/2022 ANA VILLA
Green Code Cleared 3/16/2022 MICHAEL AYERS
Historic Resource Verification Cleared 3/18/2022 MAX LODER
Redevelopment Project Area Cleared 3/21/2022 GRACIELA ACOSTA
Eng Process Fee Ord 176,300 Cleared 3/23/2022 ANA VILLA
Community Plan Implem. Overlay Cleared 4/11/2022 NORALI MARTINEZ
DAS Clearance Cleared 4/20/2022 FARSHAD ALIMOHAMADI

Contact Information

Contractor Verticon Builders Inc; Lic. No.: 746474-B 11721 WHITTER BLVD 356      WHITTIER, CA 90601

Inspector Information

MICHAEL PETRUSKO, (310) 732-4552 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/17/2022 Approved JOEY BUCHANAN
Footing/Foundation/Slab 6/27/2022 Conditional Approval JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 6/28/2022 Approved JOEY BUCHANAN
Footing/Foundation/Slab 6/28/2022 Approved JOEY BUCHANAN
Light Gage Steel Frame 8/12/2022 Approved DAVID TSAU
Insulation 8/15/2022 Approved JOEY BUCHANAN
Wood Frame 8/15/2022 Partial Approval JOEY BUCHANAN
Drywall Nailing 8/19/2022 Approved JOEY BUCHANAN
T-Bar Ceiling 9/22/2022 Approved JOEY BUCHANAN
Green Building Rough 9/29/2022 Approved JOEY BUCHANAN
Pre-Inspection 10/25/2022 Approved JOEY BUCHANAN
Reinforced Masonry Frame 10/28/2022 Approved JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 10/28/2022 SGSOV Approved JOEY BUCHANAN
Final 11/4/2022 Conditional Approval JOEY BUCHANAN
Green Building Final 11/4/2022 Approved JOEY BUCHANAN
Pre-Inspection 11/4/2022 Approved JOEY BUCHANAN
Smoke Detectors 11/4/2022 Approved JOEY BUCHANAN
Special/Order Compliance 11/4/2022 Approved JOEY BUCHANAN