3925 S COOLIDGE AVE 90066

Certificate Information: 3925 S COOLIDGE AVE 90066

Application / Permit
21016-10000-57871
Plan Check / Job No.
B21LA23261
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ADU PER STATE LAW
Permit Issued
Issued on 1/10/2022
Issuing Office
Current Status
CofO Issued on 1/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/13/2021 APPLICANT
Assigned to Plan Check Engineer 12/14/2021 CARLOS MONTES
Corrections Issued 12/15/2021 CARLOS MONTES
Plan Check Approved 1/1/2022 CARLOS MONTES
Issued 1/10/2022 APPLICANT
CofO in Progress 1/17/2023 RICHARD STEINBACH
Permit Finaled 1/17/2023 DANIEL ORRANTE
CofO Issued 1/17/2023 DANIEL ORRANTE
Permit Finaled 1/17/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/20/2021 NIKTA MOUSAVI
Sewer availability Cleared 12/20/2021 NIKTA MOUSAVI
Eng Process Fee Ord 176,300 Cleared 12/21/2021 NIKTA MOUSAVI
Specific Plan Cleared 12/22/2021 VALERIA CEJA

Contact Information

Contractor 8a General Construction; Lic. No.: 1020625-B 11660 EL GRANADA AVE      LYNWOOD, CA 90262

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/18/2022 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 2/18/2022 Approved ENRIQUE MIRELES
Underground Mechanical 2/18/2022 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 2/25/2022 No Access for Inspection KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 5/11/2022 Approved PATRICK QUALEY
BUILDING-Rough-Frame 5/19/2022 Corrections Issued PATRICK QUALEY
ELECTRICAL-Rough 5/19/2022 Corrections Issued PATRICK QUALEY
HVAC-Rough 5/19/2022 Approved PATRICK QUALEY
Interior/Exterior Lathing 5/19/2022 Conditional Approval PATRICK QUALEY
PLUMBING-Rough 5/19/2022 Approved PATRICK QUALEY
Insulation 5/26/2022 Corrections Issued CLAYTON GRAHAM
Shower Pan 5/26/2022 Approved CLAYTON GRAHAM
BUILDING-Rough-Frame 8/10/2022 Approved JESUS RODRIGUEZ
Green Building Rough 8/10/2022 Approved JESUS RODRIGUEZ
Insulation 8/10/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 8/10/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 8/24/2022 Corrections Issued JESUS RODRIGUEZ
Final 11/15/2022 Corrections Issued JESUS RODRIGUEZ
Green Building Final 11/15/2022 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 11/15/2022 SGSOV Not Ready JESUS RODRIGUEZ
Smoke Detectors 11/15/2022 Approved JESUS RODRIGUEZ
Final 12/12/2022 Not Ready for Inspection JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 12/12/2022 SGSOV Not Ready JESUS RODRIGUEZ
ELECTRICAL-Final 1/13/2023 Approved JESUS RODRIGUEZ
Final 1/13/2023 Partial Approval JESUS RODRIGUEZ
HVAC-Final 1/13/2023 Approved JESUS RODRIGUEZ
PLUMBING-Final 1/13/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 1/13/2023 SGSOV Approved JESUS RODRIGUEZ
Service/Power Release 1/13/2023 Approved JESUS RODRIGUEZ