1122 W KIPLING AVE 90041

Certificate Information: 1122 W KIPLING AVE 90041

Application / Permit
21016-10000-57852
Plan Check / Job No.
B21LA23244
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Eplan: Soft-Story seismic retrofit per LABC Chapter 93: USING ONE SPECIAL CANTILEVER COLUMN WITH GRADE BEAM
Permit Issued
Issued on 3/24/2022
Issuing Office
Current Status
CofC Issued on 3/4/2024

Permit Application Status History

Submitted 12/14/2021 APPLICANT
Assigned to Plan Check Engineer 1/12/2022 HANS SANTIAGO
Corrections Issued 1/18/2022 HANS SANTIAGO
Quality Review Completed 1/20/2022 SAI KHUM
Plan Check Approved 2/8/2022 ANDREW SANTIAGO
Issued 3/24/2022 APPLICANT
OK for CofC 5/31/2022 BRUCE CAMPBELL
CofC Issued 3/4/2024 WINSTON DUNNING

Permit Application Clearance Information

Tenant Habitability Plan Cleared 3/22/2022 MICHAEL SOTO

Contact Information

Contractor Zebra Construction Inc; Lic. No.: 1055609-B 2523 S ROBERTSON BLVD      LOS ANGELES, CA 90034
Engineer Tajvidi,, Seyed Mohammad; Lic. No.: NA84559       ,

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/19/2022 Approved BRUCE CAMPBELL
Deputy Steel/Welding 4/26/2022 Conditional Approval BRUCE CAMPBELL
Excavation/Setback/Form/Re-Bar 4/28/2022 Approved BRUCE CAMPBELL
Footing/Foundation/Slab 4/28/2022 Approved BRUCE CAMPBELL
Structural Steel Frame 4/28/2022 Approved BRUCE CAMPBELL
Wood Frame 4/28/2022 Approved BRUCE CAMPBELL
Deputy Drilled-In Anchors 4/29/2022 Conditional Approval DARRYL ARNOLD
Interior/Exterior Lathing 5/16/2022 Approved BRUCE CAMPBELL
SGSOV-Seismic Gas S/O Valve 5/24/2022 SGSOV Approved BRUCE CAMPBELL
Smoke Detectors 5/27/2022 Approved BRUCE CAMPBELL
Final 5/31/2022 OK for CofC BRUCE CAMPBELL