1423 W 20TH ST 1-8 90007
Certificate Information: 1423 W 20TH ST 1-8 90007
- Application / Permit
- 21016-10000-56911
- Plan Check / Job No.
- B21LA22849
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT STORAGE ROOM IN APARTMENT TO A NEW ACCESSORY DWELLING UNIT PER ORDINANCE.
- Permit Issued
- Issued on 8/19/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2021 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 12/20/2021 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 12/21/2021 | SAI KHUM |
| Building Plans Picked Up | 1/18/2022 | APPLICANT |
| Green Plans Picked Up | 2/24/2022 | APPLICANT |
| Plan Check Approved | 6/7/2022 | FARSHAD ALIMOHAMADI |
| Issued | 8/19/2022 | APPLICANT |
| CofO in Progress | 1/15/2025 | JEROME BLACKWOOD |
| CofO Issued | 1/21/2025 | ERNESTO CORRAL |
| Permit Finaled | 1/21/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 1/21/2022 | JEANIE LAM |
| Sewer availability | Cleared | 1/21/2022 | JEANIE LAM |
| Tenant Habitability Plan | Cleared | 2/15/2022 | RICHARD BRINSON |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2022 | JEANIE LAM |
| Green Code | Cleared | 5/3/2022 | FARSHAD ALIMOHAMADI |
Contact Information
| Architect | Sonn,, Byung Y; Lic. No.: C17362 | 2205 VENICE BLVD #12 LOS ANGELES, CA 90006 |
| Contractor | Owner-Builder | , |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/24/2022 | Not Ready for Inspection | KATY RAMIREZ |
| Pre-Inspection | 10/6/2022 | Partial Inspection | GREGORY POMISH |
| Green Building Rough | 9/11/2023 | No Access for Inspection | VAHE KELEDJIAN |
| Insulation | 9/11/2023 | No Access for Inspection | VAHE KELEDJIAN |
| METHANE-Rough | 9/11/2023 | No Access for Inspection | VAHE KELEDJIAN |
| Pre-Inspection | 9/11/2023 | No Access for Inspection | VAHE KELEDJIAN |
| Wood Frame | 9/11/2023 | No Access for Inspection | VAHE KELEDJIAN |
| Pre-Inspection | 11/2/2023 | Corrections Issued | RAMAZANALI ALMASI |
| Insulation | 12/19/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Pre-Inspection | 12/19/2023 | Partial Inspection | JEROME BLACKWOOD |
| Structural Steel Frame | 12/19/2023 | Partial Inspection | JEROME BLACKWOOD |
| Wall Anchors | 12/19/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Final | 4/22/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Final | 4/22/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Rough | 4/22/2024 | Not Ready for Inspection | RAFAEL CORTES |
| METHANE-Final | 4/22/2024 | Not Ready for Inspection | RAFAEL CORTES |
| METHANE-Rough | 4/22/2024 | Not Ready for Inspection | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 4/22/2024 | SGSOV Not Ready | RAFAEL CORTES |
| Smoke Detectors | 4/22/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 4/22/2024 | Partial Approval | RAFAEL CORTES |
| Final | 1/7/2025 | OK to Issue CofO | JEROME BLACKWOOD |
| Green Building Final | 1/7/2025 | Approved | JEROME BLACKWOOD |
| Green Building Rough | 1/7/2025 | Approved | JEROME BLACKWOOD |
| METHANE-Final | 1/7/2025 | Approved | JEROME BLACKWOOD |
| METHANE-Rough | 1/7/2025 | Approved | JEROME BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 1/7/2025 | SGSOV Approved | JEROME BLACKWOOD |
| Smoke Detectors | 1/7/2025 | Approved | JEROME BLACKWOOD |
| Wood Frame | 1/7/2025 | Approved | JEROME BLACKWOOD |