440-442 W WREN DR 90065

Certificate Information: 440-442 W WREN DR 90065

Application / Permit
21016-10000-56901
Plan Check / Job No.
B21LA22824
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) GARAGE, (E) STORAGE AND (E) BATHROOM TO ACCESSORY DWELLING UNIT PER CA GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 3/16/2022
Issuing Office
Current Status
CofO Issued on 8/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/6/2021 APPLICANT
Assigned to Plan Check Engineer 12/9/2021 GEORGE ALVAREZ
Corrections Issued 12/9/2021 GEORGE ALVAREZ
Applicant returned to address corrections 12/30/2021 SINA KHOSRAVI
Applicant returned to address corrections 1/15/2022 LUKE GONZALES
Applicant returned to address corrections 2/23/2022 STANLEY RAAP
Plan Check Approved 3/16/2022 STANLEY RAAP
Issued 3/16/2022 APPLICANT
Building Plans Picked Up 3/22/2022 APPLICANT
CofO in Progress 8/13/2022 OSVALDO PARAMO
CofO in Progress 8/13/2022 OSVALDO PARAMO
Permit Finaled 8/23/2022 DEROLD HAUFF
CofO Issued 8/23/2022 DEROLD HAUFF
Permit Finaled 8/23/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/23/2021 JEANETTE VONG
Sewer availability Cleared 12/23/2021 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 1/5/2022 JEANETTE VONG
Specific Plan Cleared 2/8/2022 NASHYA JENSEN
Grading Pre-Inspection Cleared 2/9/2022 ROBERT HUGHES
Construction near power lines Cleared 2/17/2022 RIDWAN HARDY
Construction within easement Cleared 2/17/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Jung,, Jiwon; Lic. No.: C89281 2700 E 2ND ST      LOS ANGELES, CA 90033

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/12/2022 Conditional Approval OSVALDO PARAMO
ELECTRICAL-Rough 4/27/2022 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 4/27/2022 Corrections Issued OSVALDO PARAMO
HVAC-Rough 4/27/2022 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 4/27/2022 Not Ready for Inspection OSVALDO PARAMO
Wood Frame 4/27/2022 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 5/4/2022 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 5/10/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 5/16/2022 Approved OSVALDO PARAMO
ELECTRICAL-Rough 5/18/2022 Approved OSVALDO PARAMO
HVAC-Rough 5/18/2022 Approved OSVALDO PARAMO
PLUMBING-Rough 5/18/2022 Approved OSVALDO PARAMO
Insulation 5/25/2022 Approved OSVALDO PARAMO
Wood Frame 5/25/2022 Approved OSVALDO PARAMO
Drywall Nailing 6/13/2022 Approved OSVALDO PARAMO
Interior/Exterior Lathing 6/13/2022 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 7/19/2022 Approved AMY COLIN
ELECTRICAL-Final 7/19/2022 Approved AMY COLIN
Final 7/19/2022 Not Ready for Inspection AMY COLIN
Green Building Final 7/19/2022 Corrections Issued AMY COLIN
Green Building Rough 7/19/2022 Approved AMY COLIN
HVAC-Final 7/19/2022 Approved AMY COLIN
PLUMBING-Final 7/19/2022 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 7/19/2022 SGSOV Approved AMY COLIN
Smoke Detectors 7/19/2022 Approved AMY COLIN
Final 8/10/2022 OK to Issue CofO OSVALDO PARAMO
Green Building Final 8/10/2022 Approved OSVALDO PARAMO