11474 W LA MAIDA ST 91601
Certificate Information: 11474 W LA MAIDA ST 91601
- Application / Permit
- 21016-10000-56553
- Plan Check / Job No.
- B21LA22671
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- COVERT EXISTING GARAGE INTO AN ACCESSOR DWELLING UNIT PER ORDINANCE. (2 OF 2)
- Permit Issued
- Issued on 4/13/2022
- Issuing Office
- Current Status
- CofO Issued on 1/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2021 | MICHAEL LOPEZ |
| Corrections Issued | 1/13/2022 | MICHAEL LOPEZ |
| Quality Review Completed | 1/19/2022 | KEN GILL |
| Applicant returned to address corrections | 3/8/2022 | MICHAEL LOPEZ |
| Plan Check Approved | 3/31/2022 | MICHAEL LOPEZ |
| Issued | 4/13/2022 | APPLICANT |
| Building Plans Picked Up | 4/15/2022 | APPLICANT |
| CofO in Progress | 12/28/2022 | JACK KARGODORIAN |
| CofO Issued | 1/12/2023 | MICHAEL SMITH |
| Permit Finaled | 1/12/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/12/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 1/12/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/26/2022 | JOSE DUARTE-DIAZ |
| Specific Plan | Cleared | 1/26/2022 | ERIN NASH |
| Construction near power lines | Cleared | 3/9/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Seung Su; Lic. No.: S5909 | 15808 APOLLO PLACE GARDENA, CA 90249 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/20/2022 | Not Ready for Inspection | DAVID MATSON |
| Deputy Reinf. Concrete | 5/6/2022 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2022 | Corrections Issued | CALEB MEISTER |
| Interior/Exterior Lathing | 8/3/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 8/3/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 8/5/2022 | Partial Approval | THOMAS FINNILA |
| Underground Mechanical | 8/5/2022 | Partial Approval | THOMAS FINNILA |
| HVAC-Rough | 8/12/2022 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 8/12/2022 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 8/19/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 8/19/2022 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 8/19/2022 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 8/22/2022 | Approved | JACK KARGODORIAN |
| Green Building Rough | 8/22/2022 | Approved | JACK KARGODORIAN |
| MERV13>=Rough | 8/22/2022 | Approved | JACK KARGODORIAN |
| Wood Frame | 8/22/2022 | Approved | JACK KARGODORIAN |
| Insulation | 8/26/2022 | Approved | CALEB MEISTER |
| Shower Pan | 8/31/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Drywall Nailing | 9/27/2022 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 10/3/2022 | Approved | THOMAS FINNILA |
| Shower Pan | 10/3/2022 | Approved | THOMAS FINNILA |
| Final | 12/2/2022 | Not Ready for Inspection | JOHN COLEMAN |
| Green Building Final | 12/2/2022 | Not Ready for Inspection | JOHN COLEMAN |
| MERV13>=Final | 12/2/2022 | Not Ready for Inspection | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 12/2/2022 | SGSOV Not Ready | JOHN COLEMAN |
| Smoke Detectors | 12/2/2022 | Not Ready for Inspection | JOHN COLEMAN |
| Final | 12/14/2022 | Conditional Approval | JOHN COLEMAN |
| Green Building Final | 12/14/2022 | Approved | JOHN COLEMAN |
| MERV13>=Final | 12/14/2022 | Approved | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 12/14/2022 | SGSOV Gas Company | JOHN COLEMAN |
| Smoke Detectors | 12/14/2022 | Approved | JOHN COLEMAN |
| Final | 12/27/2022 | OK to Issue CofO | JACK KARGODORIAN |