11474 W LA MAIDA ST 91601

Certificate Information: 11474 W LA MAIDA ST 91601

Application / Permit
21016-10000-56553
Plan Check / Job No.
B21LA22671
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
COVERT EXISTING GARAGE INTO AN ACCESSOR DWELLING UNIT PER ORDINANCE. (2 OF 2)
Permit Issued
Issued on 4/13/2022
Issuing Office
Current Status
CofO Issued on 1/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/3/2021 APPLICANT
Assigned to Plan Check Engineer 12/16/2021 MICHAEL LOPEZ
Corrections Issued 1/13/2022 MICHAEL LOPEZ
Quality Review Completed 1/19/2022 KEN GILL
Applicant returned to address corrections 3/8/2022 MICHAEL LOPEZ
Plan Check Approved 3/31/2022 MICHAEL LOPEZ
Issued 4/13/2022 APPLICANT
Building Plans Picked Up 4/15/2022 APPLICANT
CofO in Progress 12/28/2022 JACK KARGODORIAN
CofO Issued 1/12/2023 MICHAEL SMITH
Permit Finaled 1/12/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/12/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 1/12/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 1/26/2022 JOSE DUARTE-DIAZ
Specific Plan Cleared 1/26/2022 ERIN NASH
Construction near power lines Cleared 3/9/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Kim,, Seung Su; Lic. No.: S5909 15808 APOLLO PLACE      GARDENA, CA 90249

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/20/2022 Not Ready for Inspection DAVID MATSON
Deputy Reinf. Concrete 5/6/2022 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 7/27/2022 Corrections Issued CALEB MEISTER
Interior/Exterior Lathing 8/3/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Underground Mechanical 8/3/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 8/5/2022 Partial Approval THOMAS FINNILA
Underground Mechanical 8/5/2022 Partial Approval THOMAS FINNILA
HVAC-Rough 8/12/2022 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 8/12/2022 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 8/19/2022 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 8/19/2022 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 8/19/2022 Approved THOMAS FINNILA
BUILDING-Rough-Frame 8/22/2022 Approved JACK KARGODORIAN
Green Building Rough 8/22/2022 Approved JACK KARGODORIAN
MERV13>=Rough 8/22/2022 Approved JACK KARGODORIAN
Wood Frame 8/22/2022 Approved JACK KARGODORIAN
Insulation 8/26/2022 Approved CALEB MEISTER
Shower Pan 8/31/2022 Not Ready for Inspection THOMAS FINNILA
Drywall Nailing 9/27/2022 Approved DAVID ANDERSON
Interior/Exterior Lathing 10/3/2022 Approved THOMAS FINNILA
Shower Pan 10/3/2022 Approved THOMAS FINNILA
Final 12/2/2022 Not Ready for Inspection JOHN COLEMAN
Green Building Final 12/2/2022 Not Ready for Inspection JOHN COLEMAN
MERV13>=Final 12/2/2022 Not Ready for Inspection JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 12/2/2022 SGSOV Not Ready JOHN COLEMAN
Smoke Detectors 12/2/2022 Not Ready for Inspection JOHN COLEMAN
Final 12/14/2022 Conditional Approval JOHN COLEMAN
Green Building Final 12/14/2022 Approved JOHN COLEMAN
MERV13>=Final 12/14/2022 Approved JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 12/14/2022 SGSOV Gas Company JOHN COLEMAN
Smoke Detectors 12/14/2022 Approved JOHN COLEMAN
Final 12/27/2022 OK to Issue CofO JACK KARGODORIAN