11827 W VENICE BLVD 90066
Certificate Information: 11827 W VENICE BLVD 90066
- Application / Permit
- 21016-10000-56000
- Plan Check / Job No.
- B21LA22338
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (18) Child Care Facility
- Work Description
- CHANGE OF USE OF (E) CHURCH/SCHOOL TO CHILD DAY CARE FACILITY WITH INTERIOR REMODEL.
- Permit Issued
- Issued on 5/4/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2021 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 12/16/2021 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 12/16/2021 | SAI KHUM |
| Building Plans Picked Up | 12/20/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 12/20/2021 | APPLICANT |
| Applicant returned to address corrections | 1/27/2022 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 4/28/2022 | FARSHAD ALIMOHAMADI |
| Issued | 5/4/2022 | APPLICANT |
| CofO in Progress | 8/1/2022 | SORIN CIRSTOIU |
| CofO Issued | 8/8/2022 | DAVID TSAU |
| Permit Finaled | 8/8/2022 | DAVID TSAU |
Permit Application Clearance Information
| ZA Case | Cleared | 2/3/2022 | RICHARD REASER |
| ZA Case | Cleared | 2/3/2022 | RICHARD REASER |
| ZA Case | Cleared | 2/3/2022 | RICHARD REASER |
| Sewer availability | Cleared | 2/4/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2022 | DINAH GARIN |
| Specific Plan | Cleared | 2/24/2022 | FREDDY GARCIA |
| Fire Marshal Fire Life Safety | Cleared | 4/12/2022 | MENOA AGHAJANI |
| DAS Clearance | Cleared | 4/25/2022 | FARSHAD ALIMOHAMADI |
Contact Information
| Architect | Kozin,, Ilya; Lic. No.: C33691 | 1567 HAUSER BOULEVARD LOS ANGELES, CA 90019 |
| Contractor | A & S Constructors Inc; Lic. No.: 921776-B | 937 MIRA VALLE ST MONTEREY PARK, CA 91754 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 5/19/2022 | Partial Approval | JEFF BYTHEWAY |
| Drywall Nailing | 5/23/2022 | Partial Approval | JOHN DODGE |
| Wood Frame | 5/25/2022 | Not Ready for Inspection | JOHN DODGE |
| Footing/Foundation/Slab | 6/1/2022 | Partial Approval | PAUL DAVIDSON |
| Wood Frame | 6/1/2022 | Approved | PAUL DAVIDSON |
| Drywall Nailing | 6/6/2022 | Approved | GRANT WOODS |
| Final | 7/13/2022 | Not Ready for Inspection | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 7/13/2022 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 7/13/2022 | Approved | GRANT WOODS |
| Final | 7/20/2022 | Partial Inspection | SORIN CIRSTOIU |
| Final | 8/1/2022 | OK to Issue CofO | SORIN CIRSTOIU |