4123 N WOODMAN AVE 91423

Certificate Information: 4123 N WOODMAN AVE 91423

Application / Permit
21016-10000-55998
Plan Check / Job No.
B21LA22337
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR AND EXTERIOR RENOVATION TO EXISTING 2 STORY SINGLE FAMILY DEWLLING WITH ATTACHED GARAGE. NO CHANGE IN FLOOR AREA OR HEIGHT.
Permit Issued
Issued on 6/16/2022
Issuing Office
Current Status
Permit Finaled on 4/18/2023

Permit Application Status History

Submitted 12/6/2021 APPLICANT
Assigned to Plan Check Engineer 12/16/2021 AUNG SOE
Corrections Issued 12/21/2021 AUNG SOE
Quality Review Completed 12/22/2021 EUGENE BARBEAU
Applicant returned to address corrections 2/22/2022 AUNG SOE
Plan Check Approved 2/25/2022 AUNG SOE
Building Plans Picked Up 3/4/2022 APPLICANT
Issued 6/16/2022 APPLICANT
Permit Finaled 4/17/2023 MISAEL ESPARZA

Permit Application Clearance Information

Sewer availability Cleared 1/3/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/7/2022 CARLOS AGUILERA
GPI Written Notices Cleared 2/25/2022 AUNG SOE

Contact Information

Architect Brian, Christopher Janeczko; Lic. No.: C35821 3820 TOLAND WAY      LOS ANGELES, CA 90065
Contractor Meuchel Steve Construction; Lic. No.: 795770-B 10400 KEOKUK AVE      CHATSWORTH, CA 91311
Engineer Khoury,, Nader Bulos; Lic. No.: C61402 1278 GLENNEYRE ST 201      LAGUNA BEACH, CA 92651

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/26/2022 Conditional Approval MISAEL ESPARZA
Deputy Drilled-In Anchors 10/6/2022 Partial Approval ROBERT GOLD
BUILDING-Rough-Frame 10/24/2022 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 10/24/2022 Corrections Issued MISAEL ESPARZA
HVAC-Rough 10/24/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 10/24/2022 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 11/1/2022 Partial Approval MISAEL ESPARZA
ELECTRICAL-Rough 11/1/2022 Approved MISAEL ESPARZA
HVAC-Rough 11/1/2022 Conditional Approval MISAEL ESPARZA
PLUMBING-Rough 11/1/2022 Approved MISAEL ESPARZA
Insulation 11/10/2022 Partial Approval THOMAS FINNILA
Shower Pan 11/16/2022 Approved MISAEL ESPARZA
Interior/Exterior Lathing 11/23/2022 Partial Approval MISAEL ESPARZA
Drywall Nailing 11/29/2022 Approved MISAEL ESPARZA
Interior/Exterior Lathing 11/29/2022 Partial Approval MISAEL ESPARZA
Interior/Exterior Lathing 3/24/2023 Approved MISAEL ESPARZA
ELECTRICAL-Final 4/11/2023 Corrections Issued MISAEL ESPARZA
Final 4/11/2023 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 4/11/2023 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 4/11/2023 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 4/11/2023 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 4/11/2023 Approved MISAEL ESPARZA
ELECTRICAL-Final 4/17/2023 Approved MISAEL ESPARZA
Final 4/17/2023 Permit Finaled MISAEL ESPARZA
HVAC-Final 4/17/2023 Approved MISAEL ESPARZA
PLUMBING-Final 4/17/2023 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 4/17/2023 SGSOV Approved MISAEL ESPARZA