2975 W WILSHIRE BLVD 90010
Certificate Information: 2975 W WILSHIRE BLVD 90010
- Application / Permit
- 21016-10000-55519
- Plan Check / Job No.
- B21LA22233
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- Exterior & Interior T.I. to (E) Ofiice Building: removing non-structural partitions walls @ (e) level 1 office lobby (~1,190 sf) & level 1 parking deck with updated finishes & Re-clad (E) canopy with metal panel & wrap (E) columns in metal panel .
- Permit Issued
- Issued on 8/8/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 11/8/2023
Permit Application Status History
| Submitted | 11/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2021 | GARO TELMI |
| Corrections Issued | 12/17/2021 | GARO TELMI |
| Quality Review Completed | 12/22/2021 | KEN GILL |
| Building Plans Picked Up | 12/27/2021 | APPLICANT |
| Green Plans Picked Up | 12/29/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 1/7/2022 | APPLICANT |
| Applicant returned to address corrections | 2/1/2022 | GARO TELMI |
| Applicant returned to address corrections | 3/16/2022 | GARO TELMI |
| Applicant returned to address corrections | 3/24/2022 | GARO TELMI |
| Plan Check Approved | 3/30/2022 | GARO TELMI |
| Issued | 8/8/2022 | APPLICANT |
| Permit Finaled | 10/25/2023 | DARRYL ARNOLD |
Permit Application Clearance Information
| Green Code | Cleared | 12/28/2021 | AARON COSTA |
| Historic Resource Verification | Cleared | 12/29/2021 | LAMBERT GIESSINGER |
| Metro Rail approval | Cleared | 1/10/2022 | GARO TELMI |
| DAS Clearance | Cleared | 2/9/2022 | GARO TELMI |
| Redevelopment Project Area | Cleared | 2/10/2022 | GRACIELA ACOSTA |
Contact Information
| Architect | , ; Lic. No.: C36981 | , |
| Contractor | Dreamspace Development & Construction Inc; Lic. No.: 1059952-B | 3322 WILSHIRE BLVD 105 LOS ANGELES, CA 90010 |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 3600 WILSHIRE BLVD STE 1903 LOS ANGELES, CA 90010 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 12/13/2022 | Not Ready for Inspection | RAFAEL CORTES |
| T-Bar Ceiling | 12/13/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Drywall Nailing | 12/19/2022 | Not Ready for Inspection | JEROME BLACKWOOD |
| Light Gage Steel Frame | 12/19/2022 | Not Ready for Inspection | JEROME BLACKWOOD |
| Pre-Inspection | 12/19/2022 | Corrections Issued | JEROME BLACKWOOD |
| Structural Steel Frame | 12/19/2022 | Not Ready for Inspection | JEROME BLACKWOOD |
| Light Gage Steel Frame | 1/5/2023 | Corrections Issued | TIMOTHY POWELL |
| Light Gage Steel Frame | 1/10/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Light Gage Steel Frame | 1/12/2023 | Partial Approval | TIMOTHY POWELL |
| Drywall Nailing | 1/23/2023 | Approved | ALAN MORELOS |
| Structural Steel Frame | 2/16/2023 | Corrections Issued | TIMOTHY POWELL |
| T-Bar Ceiling | 3/30/2023 | Partial Approval | VAHE KELEDJIAN |
| Light Gage Steel Frame | 4/4/2023 | Partial Approval | ALFREDO LOPEZ |
| Structural Steel Frame | 4/4/2023 | Partial Inspection | ALFREDO LOPEZ |
| Deputy Fireproofing | 4/14/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Light Gage Steel Frame | 5/5/2023 | Corrections Issued | VAHE KELEDJIAN |
| Structural Steel Frame | 5/5/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
| Light Gage Steel Frame | 5/15/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Structural Steel Frame | 5/15/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Light Gage Steel Frame | 5/17/2023 | Partial Inspection | TIMOTHY POWELL |
| Structural Steel Frame | 5/17/2023 | Partial Inspection | TIMOTHY POWELL |
| Light Gage Steel Frame | 6/1/2023 | Partial Approval | TIMOTHY POWELL |
| Structural Steel Frame | 6/1/2023 | Partial Approval | TIMOTHY POWELL |
| Final | 6/28/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Green Building Final | 6/28/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| SGSOV-Seismic Gas S/O Valve | 6/28/2023 | SGSOV Not Ready | TIMOTHY POWELL |
| Smoke Detectors | 6/28/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Final | 7/7/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Green Building Final | 7/7/2023 | Approved | TIMOTHY POWELL |
| SGSOV-Seismic Gas S/O Valve | 7/7/2023 | SGSOV Not Ready | TIMOTHY POWELL |
| Smoke Detectors | 7/7/2023 | Approved | TIMOTHY POWELL |
| Final | 10/25/2023 | Permit Finaled | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 10/25/2023 | SGSOV Approved | DARRYL ARNOLD |