649 N PARKMAN AVE 90026
Certificate Information: 649 N PARKMAN AVE 90026
- Application / Permit
- 21016-10000-55328
- Plan Check / Job No.
- B21LA22111
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. Conversion of first floor of an (E) detached 2-story garage and storeroom into an ADU per state law GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 8/25/2022
- Issuing Office
- Current Status
- CofO Issued on 6/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/30/2021 | ZAW HAN |
| Corrections Issued | 12/1/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 7/23/2022 | ZAW HAN |
| Plan Check Approved | 7/27/2022 | ZAW HAN |
| Issued | 8/25/2022 | APPLICANT |
| CofO in Progress | 5/29/2024 | FREDDIE RIVERA |
| No Progress | 5/29/2024 | SCOTT FINNILA |
| CofO in Progress | 5/29/2024 | SCOTT FINNILA |
| Permit Finaled | 6/25/2024 | DEROLD HAUFF |
| CofO Issued | 6/25/2024 | DEROLD HAUFF |
| Permit Finaled | 6/25/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/5/2022 | ABEL CASILLAS |
| Sewer availability | Cleared | 4/5/2022 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2022 | ABEL CASILLAS |
| Grading Pre-Inspection | Cleared | 7/27/2022 | ROBERT HUGHES |
Contact Information
| Architect | Vilppu,, Lydia Nadine; Lic. No.: C31349 | 3108 GLENDALE BLVD #512 LOS ANGELES, CA 90039 |
| Architect | Vilppu,, Lydia Nadine; Lic. No.: NA31349 | , |
| Contractor | Owner-Builder | , |
| Engineer | Alferez,, Vicente Narvaez; Lic. No.: C53875 | 460 E CARSON PLAZA DR STE 212 CARSON, CA 90746 |
| Engineer | Alferez,, Vicente Narvaez; Lic. No.: NA53875 | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/3/2023 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Rough | 5/8/2023 | Partial Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 5/8/2023 | Corrections Issued | FREDDIE RIVERA |
| Underground Mechanical | 5/8/2023 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2023 | Approved | FREDDIE RIVERA |
| MERV13>=Rough | 6/26/2023 | Approved | FREDDIE RIVERA |
| METHANE-Rough | 6/26/2023 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 6/26/2023 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 7/6/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 7/6/2023 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 7/6/2023 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 7/28/2023 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Rough | 8/1/2023 | Conditional Approval | FREDDIE RIVERA |
| Shower Pan | 8/1/2023 | Partial Inspection | FREDDIE RIVERA |
| Wood Frame | 8/1/2023 | Partial Approval | FREDDIE RIVERA |
| Insulation | 9/5/2023 | Approved | JOSH MEISTER |
| HVAC-Rough | 9/8/2023 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 9/18/2023 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 9/18/2023 | Approved | JOSH MEISTER |
| ELECTRICAL-Final | 1/23/2024 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Final | 1/23/2024 | No Access for Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 2/8/2024 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 2/8/2024 | Corrections Issued | FREDDIE RIVERA |
| Final | 2/8/2024 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Final | 2/8/2024 | Approved | FREDDIE RIVERA |
| MERV13>=Final | 2/8/2024 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 2/8/2024 | Corrections Issued | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 2/8/2024 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 2/8/2024 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 3/26/2024 | Approved | THOMAS LOGRASSO |
| PLUMBING-Final | 3/26/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 4/2/2024 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Final | 4/2/2024 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 4/2/2024 | SGSOV Approved | FREDDIE RIVERA |
| Final | 5/3/2024 | OK to Issue CofO | FREDDIE RIVERA |