(1) Dwelling - Single Family
Work Description
REMODEL SINGLE FAMILY DWELLING - CONVERT FAMILY ROOM INTO BEDROOM AND CONVERT UTILITY AREA AND NOOK INTO MASTER BATHROOM AND CLOSET. REPAIR MISC. DRY WALL AND RELOCATE LAUNDRY TO HALLWAY. TOTAL AREA OF ALTERATION/REMODEL: 360 SQFT ADD 36 SQFT REAR PORCH
Permit Issued
Issued on 5/9/2022
Issuing Office
Current Status
CofO Issued on 2/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/22/2021 APPLICANT
Assigned to Plan Check Engineer 11/23/2021 JOSEPH RAFOLS
Corrections Issued 11/23/2021 JOSEPH RAFOLS
Applicant returned to address corrections 12/28/2021 TSE MING HUANG
Plan Check Approved 4/14/2022 ADAM HEGAZI
Issued 5/9/2022 APPLICANT
Building Plans Picked Up 5/12/2022 APPLICANT
CofO in Progress 1/13/2023 CALEB MEISTER
No Progress 1/13/2023 CALEB MEISTER
CofO in Progress 2/15/2023 CALEB MEISTER
CofO in Progress 2/15/2023 CALEB MEISTER
Permit Finaled 2/19/2023 DEROLD HAUFF
CofO Issued 2/19/2023 DEROLD HAUFF
Permit Finaled 2/19/2023 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 1/5/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 1/6/2022 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,
Engineer Hamilton,, John O; Lic. No.: C53284 P O BOX 866      HAWTHORNE, CA 90251

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 6/3/2022 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 6/3/2022 Approved STUART CHAPMAN
HVAC-Rough 6/3/2022 Approved STUART CHAPMAN
PLUMBING-Rough 6/3/2022 Approved STUART CHAPMAN
Insulation 7/15/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 7/27/2022 Not Ready for Inspection STUART CHAPMAN
Insulation 8/2/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 8/2/2022 Partial Approval STUART CHAPMAN
Drywall Nailing 8/16/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 8/16/2022 Not Ready for Inspection STUART CHAPMAN
Shower Pan 10/7/2022 Approved JULIAN AMAYA
Underground Mechanical 10/7/2022 Approved JULIAN AMAYA
BUILDING-Rough-Frame 12/22/2022 Not Ready for Inspection CALEB MEISTER
Final 12/22/2022 Corrections Issued CALEB MEISTER
Footing/Foundation/Slab 12/22/2022 Not Ready for Inspection CALEB MEISTER
Green Building Final 12/22/2022 Not Ready for Inspection CALEB MEISTER
Green Building Rough 12/22/2022 Not Ready for Inspection CALEB MEISTER
SGSOV-Seismic Gas S/O Valve 12/22/2022 SGSOV Not Ready CALEB MEISTER
Smoke Detectors 12/22/2022 Not Ready for Inspection CALEB MEISTER
BUILDING-Rough-Frame 1/6/2023 Approved CALEB MEISTER
Final 1/6/2023 Conditional Approval CALEB MEISTER
Footing/Foundation/Slab 1/6/2023 Approved CALEB MEISTER
Green Building Final 1/6/2023 Approved CALEB MEISTER
Green Building Rough 1/6/2023 Approved CALEB MEISTER
SGSOV-Seismic Gas S/O Valve 1/6/2023 SGSOV Approved CALEB MEISTER
Smoke Detectors 1/6/2023 Approved CALEB MEISTER
Final 1/12/2023 OK to Issue CofO CALEB MEISTER
Final 2/15/2023 OK to Issue CofO CALEB MEISTER