(22) Storage Building
Work Description
2nd FLOOR BUILD OUT, T.I. OF (E) OFFICE/ DATA CENTETR BUILDING. ADD STRUCTURAL PLATFORM FOR ROOF TOP EQUIPMENT/CHILLER.
Permit Issued
Issued on 8/2/2022
Issuing Office
Metro
Current Status
Permit Finaled on 7/29/2025

Permit Application Status History

Submitted 11/19/2021 APPLICANT
Green Plans Picked Up 11/30/2021 APPLICANT
Assigned to Plan Check Engineer 12/2/2021 ARMEN JIVALAGIAN
Corrections Issued 12/9/2021 ARMEN JIVALAGIAN
Quality Review Completed 12/9/2021 PETER KIM
Building Plans Picked Up 12/16/2021 APPLICANT
Applicant returned to address corrections 2/8/2022 ARMEN JIVALAGIAN
Applicant returned to address corrections 4/27/2022 ARMEN JIVALAGIAN
Plan Check Approved 6/24/2022 ARMEN JIVALAGIAN
Issued 8/2/2022 APPLICANT
Permit Finaled 7/29/2025 RONALD JIMENEZ

Permit Application Clearance Information

City Hist. Cultural Monument Cleared 12/16/2021 LAMBERT GIESSINGER
Historic Resource Verification Cleared 12/16/2021 LAMBERT GIESSINGER
Historic monument Cleared 12/16/2021 LAMBERT GIESSINGER
Redevelopment Project Area Cleared 12/27/2021 DAVID URITA
Miscellaneous Cleared 12/28/2021 LOUIS ORTEGA
Miscellaneous Cleared 12/28/2021 LOUIS ORTEGA
Miscellaneous Cleared 12/28/2021 LOUIS ORTEGA
ZI Cleared 12/28/2021 LOUIS ORTEGA
Eng Process Fee Ord 176,300 Cleared 12/29/2021 AMAAN MALIK
Roof/Waste drainage to street Cleared 12/29/2021 AMAAN MALIK
Sewer availability Cleared 1/4/2022 AMAAN MALIK
Specific Plan Cleared 1/4/2022 YI LU
Construction near power lines Cleared 2/4/2022 WALTER RAMIREZ
Construction within easement Cleared 2/4/2022 WALTER RAMIREZ
Metro Rail approval Cleared 2/25/2022 ARMEN JIVALAGIAN
Green Code Cleared 3/3/2022 AARON COSTA
DAS Clearance Cleared 3/10/2022 SHINE LIN

Contact Information

Architect Ruch,, Scott M; Lic. No.: C36046 401 N HOUSTON STREET      DALLAS, TX 75202
Contractor Whiting-Turner Contracting Company The; Lic. No.: 311107-A 800 R STREET      SACRAMENTO, CA 95811
Engineer Chung,, Justin Jeesung; Lic. No.: S6038 950 S GRAND AVE 4TH FLOOR      LOS ANGELES, CA 90015

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/8/2022 Partial Inspection MARK FERRARI
Deputy Drilled-In Anchors 1/4/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 1/4/2023 Conditional Approval MICHAEL ROSENBERG
Drywall Nailing 1/11/2023 Partial Approval RAFAEL CORTES
Light Gage Steel Frame 1/11/2023 Partial Approval RAFAEL CORTES
Drywall Nailing 1/23/2023 Partial Approval RAFAEL CORTES
Light Gage Steel Frame 1/23/2023 Partial Approval RAFAEL CORTES
Drywall Nailing 2/1/2023 Partial Approval JULIAN CAPUCETTI
Light Gage Steel Frame 2/7/2023 Partial Approval RAFAEL CORTES
Deputy Reinf. Concrete 2/9/2023 Conditional Approval MICHAEL ROSENBERG
Drywall Nailing 2/15/2023 Partial Approval RAFAEL CORTES
Light Gage Steel Frame 2/22/2023 Partial Approval JAIME RIOS
Drywall Nailing 3/3/2023 Partial Approval ALAN MORELOS
Deputy Drilled-In Anchors 4/26/2023 Conditional Approval MICHAEL ROSENBERG
T-Bar Ceiling 7/19/2023 Corrections Issued RAFAEL CORTES
T-Bar Ceiling 7/21/2023 Partial Approval RAFAEL CORTES
T-Bar Ceiling 7/24/2023 Not Ready for Inspection RAFAEL CORTES
Deputy Steel/Welding 9/7/2023 Conditional Approval JULIAN CAPUCETTI
Final 9/12/2023 Not Ready for Inspection RAFAEL CORTES
Green Building Final 9/12/2023 Not Ready for Inspection RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 9/12/2023 SGSOV Not Ready RAFAEL CORTES
Smoke Detectors 9/12/2023 Approved RAFAEL CORTES
Final 9/15/2023 Not Ready for Inspection RAFAEL CORTES
Green Building Final 9/15/2023 Not Ready for Inspection RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 9/15/2023 SGSOV Not Ready RAFAEL CORTES
Deputy Steel/Welding 11/29/2023 Conditional Approval MICHAEL ROSENBERG
Final 7/22/2025 Conditional Approval RONALD JIMENEZ
Green Building Final 7/22/2025 Approved RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 7/22/2025 SGSOV Approved RONALD JIMENEZ
Final 7/29/2025 Permit Finaled RONALD JIMENEZ