840 3/4 W 64TH ST 90044
Certificate Information: 840 3/4 W 64TH ST 90044
- Application / Permit
- 21016-10000-54970
- Plan Check / Job No.
- B21LA21792
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- GARAGE TO BE CONVERTED INTO A.D.U.
- Permit Issued
- Issued on 7/28/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/7/2021 | JOSEPH RAFOLS |
| Corrections Issued | 12/8/2021 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 4/5/2022 | TSE MING HUANG |
| Applicant returned to address corrections | 6/30/2022 | RAHEL BEYENE |
| Building Plans Picked Up | 6/30/2022 | APPLICANT |
| Plan Check Approved | 7/28/2022 | DANIEL SANJUAN |
| Issued | 7/28/2022 | APPLICANT |
| CofO in Progress | 7/21/2023 | MICHAEL LEWIS |
| Permit Finaled | 7/30/2023 | DEROLD HAUFF |
| CofO Issued | 7/30/2023 | DEROLD HAUFF |
| Permit Finaled | 7/30/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/30/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 6/30/2022 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 6/30/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 6/30/2022 | STEVE MELGAR |
| Tenant Habitability Plan | Cleared | 7/1/2022 | MICHAEL SOTO |
| Construction near power lines | Cleared | 7/6/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/5/2022 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 10/7/2022 | Partial Approval | HORACE FULTZ |
| Footing/Foundation/Slab | 10/14/2022 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2022 | Approved | RYAN SALAZAR |
| Wood Frame | 10/21/2022 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 11/22/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 11/22/2022 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 11/22/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 11/22/2022 | Corrections Issued | LILIANA PORTILLO |
| Sewer | 11/22/2022 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 11/22/2022 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 11/29/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 11/29/2022 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 11/29/2022 | Approved | LILIANA PORTILLO |
| Insulation | 12/7/2022 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 12/7/2022 | Partial Approval | LILIANA PORTILLO |
| Drywall Nailing | 1/3/2023 | Corrections Issued | LILIANA PORTILLO |
| Insulation | 1/3/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 1/3/2023 | Approved | LILIANA PORTILLO |
| Shower Pan | 1/3/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Drywall Nailing | 1/6/2023 | Approved | LILIANA PORTILLO |
| Shower Pan | 1/6/2023 | Approved | LILIANA PORTILLO |
| Pre-Inspection | 5/3/2023 | Approved | MICHAEL LEWIS |
| Pre-Inspection | 5/22/2023 | Approved | MICHAEL LEWIS |
| Final | 6/5/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 6/5/2023 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 6/5/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 6/12/2023 | Corrections Issued | STUART CHAPMAN |
| Final | 7/7/2023 | Partial Inspection | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 7/7/2023 | SGSOV Approved | MICHAEL LEWIS |
| Final | 7/12/2023 | OK to Issue CofO | MICHAEL LEWIS |