4525 W 64TH ST 90043
Certificate Information: 4525 W 64TH ST 90043
- Application / Permit
- 21016-10000-54912
- Plan Check / Job No.
- B21LA21756
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING GARAGE TO ADU PER CA Govt Code 65852.2(e)(1)(A).
- Permit Issued
- Issued on 6/9/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/29/2021 | FERNANDO FLORES |
| Corrections Issued | 11/30/2021 | FERNANDO FLORES |
| Building Plans Picked Up | 12/8/2021 | APPLICANT |
| Applicant returned to address corrections | 4/22/2022 | KHUONG TRUONG |
| Plan Check Approved | 5/9/2022 | ADAM HEGAZI |
| Issued | 6/9/2022 | APPLICANT |
| CofO in Progress | 3/14/2023 | ENRIQUE MIRELES |
| Permit Finaled | 3/16/2023 | DEROLD HAUFF |
| CofO Issued | 3/16/2023 | DEROLD HAUFF |
| Permit Finaled | 3/16/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 2/27/2022 | TINA MIRANDA |
| Address approval | Cleared | 4/5/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 4/5/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2022 | TREVOR QUAN |
| Grading Pre-Inspection | Cleared | 4/11/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Ballard Nick Construction; Lic. No.: 1010094-B | 8017 CRENSHAW BLVD INGLEWOOD, CA 90305 |
| Engineer | Stewart,, Carl; Lic. No.: C86681 | 8811 GENTLE WIND DR CORONA, CA 92883 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/28/2022 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 8/17/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 8/17/2022 | Approved | ENRIQUE MIRELES |
| Sewer | 8/17/2022 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 9/7/2022 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 9/15/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 10/12/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 10/12/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2022 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Rough | 10/12/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 10/12/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 10/14/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2022 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Rough | 10/14/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 10/14/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| Insulation | 10/17/2022 | Corrections Issued | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 10/25/2022 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 10/25/2022 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 10/25/2022 | Approved | RYAN SALAZAR |
| HVAC-Rough | 10/26/2022 | Not Ready for Inspection | RYAN SALAZAR |
| Insulation | 10/26/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 10/26/2022 | Not Ready for Inspection | RYAN SALAZAR |
| Interior/Exterior Lathing | 10/27/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 11/2/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 11/8/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 11/10/2022 | Partial Approval | LILIANA PORTILLO |
| ELECTRICAL-Final | 2/17/2023 | Approved | ENRIQUE MIRELES |
| Final | 2/17/2023 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Final | 2/17/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 2/17/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 2/17/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 2/17/2023 | Approved | ENRIQUE MIRELES |
| Final | 2/28/2023 | OK to Issue CofO | ENRIQUE MIRELES |