2923 3/4 S BRIGHTON AVE 90018

Certificate Information: 2923 3/4 S BRIGHTON AVE 90018

Application / Permit
21016-10000-54842
Plan Check / Job No.
B21LA21729
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePlan* Convert (E) 2 car garage into an ADU per ordinance.
Permit Issued
Issued on 3/31/2022
Issuing Office
Current Status
CofO Issued on 10/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/18/2021 APPLICANT
Assigned to Plan Check Engineer 11/24/2021 MICHAEL LOPEZ
Corrections Issued 11/26/2021 MICHAEL LOPEZ
Plan Check Approved 3/22/2022 MICHAEL LOPEZ
Issued 3/31/2022 APPLICANT
CofO in Progress 9/27/2023 ALIZAH MAYAGOITIA
Permit Finaled 10/4/2023 DEROLD HAUFF
CofO Issued 10/4/2023 DEROLD HAUFF
Permit Finaled 10/4/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/21/2021 KHOUNG LE
Sewer availability Cleared 12/21/2021 KHOUNG LE
Eng Process Fee Ord 176,300 Cleared 12/23/2021 KHOUNG LE
Community Plan Implem. Overlay Cleared 1/25/2022 RAFAEL FONTES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/18/2022 Corrections Issued KATHRYN BUTTERWORTH
Footing/Foundation/Slab 4/19/2022 Corrections Issued KATHRYN BUTTERWORTH
PLUMBING-Rough 4/19/2022 Partial Approval KATHRYN BUTTERWORTH
Sewer 4/19/2022 Approved KATHRYN BUTTERWORTH
Footing/Foundation/Slab 11/4/2022 Corrections Issued KATHRYN BUTTERWORTH
Footing/Foundation/Slab 11/28/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Footing/Foundation/Slab 12/6/2022 Partial Approval KATHRYN BUTTERWORTH
Footing/Foundation/Slab 12/20/2022 Approved STUART CHAPMAN
Deputy Drilled-In Anchors 12/21/2022 Conditional Approval ALEJANDRO DE ARTOLA
Gas Test 1/20/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Gas Test 2/6/2023 Corrections Issued KATHRYN BUTTERWORTH
ELECTRICAL-Rough 2/17/2023 Not Ready for Inspection STUART CHAPMAN
METHANE-Rough 2/17/2023 Approved STUART CHAPMAN
PLUMBING-Rough 2/17/2023 Approved STUART CHAPMAN
BUILDING-Rough-Frame 3/2/2023 Corrections Issued KATHRYN BUTTERWORTH
ELECTRICAL-Rough 3/2/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Green Building Rough 3/2/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 4/3/2023 Corrections Issued SCOTT FINNILA
ELECTRICAL-Rough 4/3/2023 Corrections Issued SCOTT FINNILA
Green Building Rough 4/3/2023 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 4/25/2023 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Rough 4/25/2023 Corrections Issued KATHRYN BUTTERWORTH
Interior/Exterior Lathing 4/25/2023 Partial Approval KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 5/3/2023 Corrections Issued KATHRYN BUTTERWORTH
ELECTRICAL-Rough 5/3/2023 Approved KATHRYN BUTTERWORTH
Green Building Rough 5/3/2023 Approved KATHRYN BUTTERWORTH
Insulation 5/11/2023 Approved KATHRYN BUTTERWORTH
Drywall Nailing 5/17/2023 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 5/24/2023 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 5/24/2023 Partial Approval KATHRYN BUTTERWORTH
Underground Mechanical 6/5/2023 Partial Approval KATHRYN BUTTERWORTH
Final 9/6/2023 Corrections Issued KATHRYN BUTTERWORTH
Green Building Final 9/6/2023 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 9/6/2023 SGSOV Approved KATHRYN BUTTERWORTH
Smoke Detectors 9/6/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 9/26/2023 Conditional Approval ALIZAH MAYAGOITIA
Smoke Detectors 9/26/2023 Approved ALIZAH MAYAGOITIA
Final 9/27/2023 OK to Issue CofO ALIZAH MAYAGOITIA