8317 S COLEGIO DR 90045
Certificate Information: 8317 S COLEGIO DR 90045
- Application / Permit
- 21016-10000-54614
- Plan Check / Job No.
- B21LA21610
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. CONVERT (E) DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 12/28/2021
- Issuing Office
- Current Status
- CofO Issued on 9/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/19/2021 | KEVIN MORALES |
| Corrections Issued | 11/19/2021 | KEVIN MORALES |
| Plan Check Approved | 12/20/2021 | KEVIN MORALES |
| Issued | 12/28/2021 | APPLICANT |
| CofO in Progress | 8/31/2022 | BOBBY KEY |
| Permit Finaled | 9/9/2022 | DANIEL ORRANTE |
| CofO Issued | 9/9/2022 | DANIEL ORRANTE |
| Permit Finaled | 9/9/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 11/23/2021 | FREDDY GARCIA |
| Address approval | Cleared | 11/29/2021 | DINAH GARIN |
| Sewer availability | Cleared | 11/29/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 11/30/2021 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Saiyadian, Sarnaghi, Tomik; Lic. No.: C89129 | 1171 JUSTIN AVE APT 3 GLENDALE, CA 91201 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 1/28/2022 | Approved | BOBBY KEY |
| PLUMBING-Rough | 2/2/2022 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Rough | 4/4/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 4/4/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 4/4/2022 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2022 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 4/14/2022 | Approved | BOBBY KEY |
| Underground Mechanical | 4/14/2022 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 4/27/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 4/27/2022 | Corrections Issued | BOBBY KEY |
| Green Building Rough | 4/27/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 4/27/2022 | Approved | BOBBY KEY |
| PLUMBING-Rough | 4/27/2022 | Approved | BOBBY KEY |
| Insulation | 5/5/2022 | Approved | RYAN SALAZAR |
| Drywall Nailing | 5/13/2022 | Approved | BOBBY KEY |
| Final | 5/13/2022 | Corrections Issued | BOBBY KEY |
| Final | 7/13/2022 | Corrections Issued | JESUS RODRIGUEZ |
| METHANE-Final | 7/13/2022 | Corrections Issued | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 7/13/2022 | SGSOV Not Ready | JESUS RODRIGUEZ |
| Smoke Detectors | 7/13/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 7/19/2022 | Corrections Issued | JESUS RODRIGUEZ |
| METHANE-Final | 7/19/2022 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 7/19/2022 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 7/19/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Final | 7/22/2022 | Approved | HERBERT GIRON |
| Smoke Detectors | 7/22/2022 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 7/26/2022 | Approved | BOBBY KEY |
| HVAC-Final | 7/26/2022 | Corrections Issued | BOBBY KEY |
| Final | 8/31/2022 | OK to Issue CofO | BOBBY KEY |
| HVAC-Final | 8/31/2022 | Approved | BOBBY KEY |
| Smoke Detectors | 8/31/2022 | Approved | BOBBY KEY |