7824 S CROYDON AVE 90045

Certificate Information: 7824 S CROYDON AVE 90045

Application / Permit
21016-10000-54613
Plan Check / Job No.
B21LA21609
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
DETACHED GARAGE CONVERSION TO ADU - 329 sf
Permit Issued
Issued on 12/21/2021
Issuing Office
Current Status
CofO Issued on 12/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/17/2021 APPLICANT
Assigned to Plan Check Engineer 11/19/2021 JOE VO
Corrections Issued 12/1/2021 JOE VO
Plan Check Approved 12/15/2021 JOE VO
Issued 12/21/2021 APPLICANT
CofO in Progress 12/15/2022 BOBBY KEY
Permit Finaled 12/21/2022 DANIEL ORRANTE
CofO Issued 12/21/2022 DANIEL ORRANTE
Permit Finaled 12/21/2022 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/8/2021 BRIAN MILLER
Address approval Cleared 12/13/2021 ANTHONY MAINEZ
Sewer availability Cleared 12/13/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 12/14/2021 ANTHONY MAINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/17/2022 Approved BOBBY KEY
Footing/Foundation/Slab 2/17/2022 Approved BOBBY KEY
Pre-Inspection 2/17/2022 Approved BOBBY KEY
Special/Order Compliance 3/17/2022 Partial Inspection BOBBY KEY
ELECTRICAL-Final 6/27/2022 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 6/27/2022 Partial Approval BOBBY KEY
PLUMBING-Rough 6/27/2022 Partial Approval BOBBY KEY
Special/Order Compliance 6/27/2022 Partial Approval HERBERT GIRON
ELECTRICAL-Rough 7/5/2022 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 7/5/2022 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 7/5/2022 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 7/7/2022 Approved BOBBY KEY
PLUMBING-Rough 7/7/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 7/12/2022 Partial Approval BOBBY KEY
HVAC-Rough 7/12/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 7/20/2022 Partial Approval HERBERT GIRON
Insulation 7/20/2022 Not Ready for Inspection HERBERT GIRON
Interior/Exterior Lathing 7/20/2022 Not Ready for Inspection HERBERT GIRON
BUILDING-Rough-Frame 7/22/2022 Approved HERBERT GIRON
Green Building Rough 7/22/2022 Approved HERBERT GIRON
Insulation 7/22/2022 Approved HERBERT GIRON
Interior/Exterior Lathing 7/22/2022 Partial Approval HERBERT GIRON
Drywall Nailing 7/29/2022 Approved RICHARD STEINBACH
Final 8/16/2022 Corrections Issued BOBBY KEY
Interior/Exterior Lathing 8/16/2022 Conditional Approval BOBBY KEY
Shower Pan 8/18/2022 Approved CLAYTON GRAHAM
ELECTRICAL-Final 10/31/2022 Not Ready for Inspection BOBBY KEY
HVAC-Final 10/31/2022 Not Ready for Inspection BOBBY KEY
PLUMBING-Final 10/31/2022 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Final 11/16/2022 Corrections Issued BOBBY KEY
Final 11/16/2022 Not Ready for Inspection BOBBY KEY
HVAC-Final 11/16/2022 Corrections Issued BOBBY KEY
PLUMBING-Final 11/16/2022 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 11/16/2022 SGSOV Approved BOBBY KEY
Smoke Detectors 11/16/2022 Approved BOBBY KEY
ELECTRICAL-Final 11/21/2022 Approved BOBBY KEY
Final 11/21/2022 Not Ready for Inspection BOBBY KEY
HVAC-Final 11/21/2022 Approved BOBBY KEY
Final 12/2/2022 Not Ready for Inspection HERBERT GIRON
Gas Test 12/2/2022 Corrections Issued HERBERT GIRON
Gas Test 12/6/2022 Approved HERBERT GIRON
Final 12/14/2022 OK to Issue CofO BOBBY KEY