1615 S DUNSMUIR AVE 90019
Certificate Information: 1615 S DUNSMUIR AVE 90019
- Application / Permit
- 21016-10000-54543
- Plan Check / Job No.
- B21LA21585
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: By adding wood shear wall at WEST elevation
- Permit Issued
- Issued on 9/1/2022
- Issuing Office
- Current Status
- CofC Issued on 12/19/2022
Permit Application Status History
| Submitted | 11/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2021 | HANS SANTIAGO |
| Corrections Issued | 12/27/2021 | HANS SANTIAGO |
| Quality Review Completed | 12/29/2021 | SAI KHUM |
| Applicant returned to address corrections | 4/25/2022 | HANS SANTIAGO |
| Plan Check Approved | 5/4/2022 | ANDREW SANTIAGO |
| Issued | 9/1/2022 | APPLICANT |
| OK for CofC | 12/16/2022 | DARRYL ARNOLD |
| CofC Issued | 12/19/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 8/31/2022 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Sks Construction; Lic. No.: 720390-B | 15134 FRIAR STREET VAN NUYS, CA 91411 |
| Engineer | Shaolian,, Shahab Joseph; Lic. No.: C84155 | 5104 GARDEN GROVE TARZANA, CA 91356 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/21/2022 | Corrections Issued | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 9/27/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 9/28/2022 | Corrections Issued | DARRYL ARNOLD |
| Footing/Foundation/Slab | 9/28/2022 | Approved | DARRYL ARNOLD |
| Wood Frame | 9/28/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Wood Construction | 9/29/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Wood Construction | 10/5/2022 | Conditional Approval | DARRYL ARNOLD |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2022 | Approved | DANIEL VARNUM |
| Wood Frame | 10/6/2022 | Approved | DANIEL VARNUM |
| Interior/Exterior Lathing | 10/27/2022 | Conditional Approval | DARRYL ARNOLD |
| Final | 12/16/2022 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 12/16/2022 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 12/16/2022 | Approved | DARRYL ARNOLD |