1048 1/2 S HUDSON AVE 90019

Certificate Information: 1048 1/2 S HUDSON AVE 90019

Application / Permit
21016-10000-54316
Plan Check / Job No.
B21LA21476
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) TWO CAR GARAGE AND RECREATION ROOM INTO A 1,078 SQ.FT. ACCESSORY DWELLINJG UNIT PER STATE LAW ALL WORK DONE PER WFPP
Permit Issued
Issued on 6/16/2022
Issuing Office
Metro
Current Status
CofO Issued on 3/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/17/2021 APPLICANT
Assigned to Plan Check Engineer 11/19/2021 STANLEY RAAP
Corrections Issued 11/23/2021 STANLEY RAAP
Building Plans Picked Up 12/17/2021 APPLICANT
Plan Check Approved 5/19/2022 KHUONG TRUONG
Issued 6/16/2022 APPLICANT
CofO in Progress 3/1/2023 RICHARD DOCKUS
Permit Finaled 3/4/2023 DEROLD HAUFF
CofO Issued 3/4/2023 DEROLD HAUFF
Permit Finaled 3/4/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/18/2022 STEVE MELGAR
Sewer availability Cleared 2/18/2022 STEVE MELGAR
CPC Cleared 2/22/2022 DALIA MOKAYED
CPC Cleared 2/22/2022 DALIA MOKAYED
Eng Process Fee Ord 176,300 Cleared 3/3/2022 STEVE MELGAR
Construction near power lines Cleared 4/1/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Drywall Nailing 10/25/2022 Partial Approval KATHRYN BUTTERWORTH
Interior/Exterior Lathing 10/25/2022 Corrections Issued KATHRYN BUTTERWORTH
Drywall Nailing 10/27/2022 Partial Approval MICHAEL LEWIS
Interior/Exterior Lathing 10/27/2022 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 11/16/2022 No Access for Inspection MICHAEL LEWIS
Drywall Nailing 11/16/2022 No Access for Inspection MICHAEL LEWIS
Final 11/16/2022 No Access for Inspection MICHAEL LEWIS
Green Building Final 11/16/2022 No Access for Inspection MICHAEL LEWIS
Green Building Rough 11/16/2022 No Access for Inspection MICHAEL LEWIS
METHANE-Final 11/16/2022 No Access for Inspection MICHAEL LEWIS
METHANE-Rough 11/16/2022 No Access for Inspection MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 11/16/2022 SGSOV Not Ready MICHAEL LEWIS
Smoke Detectors 11/16/2022 No Access for Inspection MICHAEL LEWIS
BUILDING-Rough-Frame 12/7/2022 Approved JEFFREY MEAD
Drywall Nailing 12/7/2022 Approved JEFFREY MEAD
Final 12/7/2022 Corrections Issued JEFFREY MEAD
Green Building Final 12/7/2022 Approved JEFFREY MEAD
Green Building Rough 12/7/2022 Approved JEFFREY MEAD
METHANE-Final 12/7/2022 Approved JEFFREY MEAD
METHANE-Rough 12/7/2022 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 12/7/2022 SGSOV Not Required JEFFREY MEAD
Smoke Detectors 12/7/2022 Not Ready for Inspection JEFFREY MEAD
Final 12/13/2022 Corrections Issued RICHARD DOCKUS
Gas Test 12/13/2022 Not Ready for Inspection RICHARD DOCKUS
Smoke Detectors 12/13/2022 Approved RICHARD DOCKUS
Final 2/22/2023 OK to Issue CofO RICHARD DOCKUS
Gas Test 2/22/2023 Approved RICHARD DOCKUS