2126 S 5TH AVE 90018

Certificate Information: 2126 S 5TH AVE 90018

Application / Permit
21016-10000-54256
Plan Check / Job No.
B21LA21446
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE AND STORAGE TO NEW A.D.U. PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 3/21/2023
Issuing Office
Metro
Current Status
CofO Issued on 8/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/22/2021 APPLICANT
Corrections Issued 11/26/2021 SINA KHOSRAVI
Assigned to Plan Check Engineer 11/30/2021 SINA KHOSRAVI
Building Plans Picked Up 12/14/2021 APPLICANT
Plan Check Approved 11/10/2022 KHUONG TRUONG
Issued 3/21/2023 APPLICANT
CofO in Progress 8/22/2023 CALEB MEISTER
Permit Finaled 8/23/2023 DEROLD HAUFF
CofO Issued 8/23/2023 DEROLD HAUFF
Permit Finaled 8/23/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/14/2022 CHRISTOPHER ROCHA
Miscellaneous Cleared 1/14/2022 DALIA MOKAYED
Miscellaneous Cleared 1/14/2022 DALIA MOKAYED
Sewer availability Cleared 1/14/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 1/18/2022 CHRISTOPHER ROCHA
Community Plan Implem. Overlay Cleared 6/13/2022 KYLE WINSTON
Tenant Habitability Plan Cleared 8/19/2022 ISMAEL HERNANDEZ
Construction near power lines Cleared 10/1/2022 RIDWAN HARDY

Contact Information

Contractor Don Construction; Lic. No.: 840108-B 28063 MEMORY LN      VALENCIA, CA 91354
Engineer Tagudar,, Fred; Lic. No.: C33612 255 W 5TH ST APT 706      SAN PEDRO, CA 90731

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/12/2023 Conditional Approval CALEB MEISTER
Excavation/Setback/Form/Re-Bar 4/13/2023 Partial Approval CALEB MEISTER
PLUMBING-Rough 4/13/2023 Partial Approval CALEB MEISTER
Sewer 4/13/2023 Approved CALEB MEISTER
Excavation/Setback/Form/Re-Bar 4/19/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 4/19/2023 Partial Approval MICHAEL LEWIS
BUILDING-Rough-Frame 5/8/2023 Not Ready for Inspection CALEB MEISTER
Gas Test 5/8/2023 Not Ready for Inspection CALEB MEISTER
MERV13>=Rough 5/8/2023 Not Ready for Inspection CALEB MEISTER
METHANE-Rough 5/8/2023 Not Ready for Inspection CALEB MEISTER
Rough-Elec/Plmb/HVAC 5/8/2023 Not Ready for Inspection CALEB MEISTER
Shower Pan 5/8/2023 Not Ready for Inspection CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 5/11/2023 Approved CALEB MEISTER
Insulation 5/11/2023 Approved CALEB MEISTER
Interior/Exterior Lathing 5/11/2023 Approved CALEB MEISTER
Drywall Nailing 5/17/2023 Approved CALEB MEISTER
ELECTRICAL-Final 5/17/2023 Not Ready for Inspection CALEB MEISTER
ELECTRICAL-Final 5/24/2023 Not Ready for Inspection CALEB MEISTER
BUILDING-Rough-Frame 6/14/2023 Approved CALEB MEISTER
Final 6/14/2023 Conditional Approval CALEB MEISTER
MERV13>=Final 6/14/2023 Approved CALEB MEISTER
MERV13>=Rough 6/14/2023 Approved CALEB MEISTER
METHANE-Final 6/14/2023 Approved CALEB MEISTER
METHANE-Rough 6/14/2023 Approved CALEB MEISTER
SGSOV-Seismic Gas S/O Valve 6/14/2023 SGSOV Approved CALEB MEISTER
Smoke Detectors 6/14/2023 Approved CALEB MEISTER
Final 8/22/2023 OK to Issue CofO CALEB MEISTER