2126 S 5TH AVE 90018
Certificate Information: 2126 S 5TH AVE 90018
- Application / Permit
- 21016-10000-54256
- Plan Check / Job No.
- B21LA21446
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE AND STORAGE TO NEW A.D.U. PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 3/21/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/22/2021 | APPLICANT |
| Corrections Issued | 11/26/2021 | SINA KHOSRAVI |
| Assigned to Plan Check Engineer | 11/30/2021 | SINA KHOSRAVI |
| Building Plans Picked Up | 12/14/2021 | APPLICANT |
| Plan Check Approved | 11/10/2022 | KHUONG TRUONG |
| Issued | 3/21/2023 | APPLICANT |
| CofO in Progress | 8/22/2023 | CALEB MEISTER |
| Permit Finaled | 8/23/2023 | DEROLD HAUFF |
| CofO Issued | 8/23/2023 | DEROLD HAUFF |
| Permit Finaled | 8/23/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/14/2022 | CHRISTOPHER ROCHA |
| Miscellaneous | Cleared | 1/14/2022 | DALIA MOKAYED |
| Miscellaneous | Cleared | 1/14/2022 | DALIA MOKAYED |
| Sewer availability | Cleared | 1/14/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 1/18/2022 | CHRISTOPHER ROCHA |
| Community Plan Implem. Overlay | Cleared | 6/13/2022 | KYLE WINSTON |
| Tenant Habitability Plan | Cleared | 8/19/2022 | ISMAEL HERNANDEZ |
| Construction near power lines | Cleared | 10/1/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Don Construction; Lic. No.: 840108-B | 28063 MEMORY LN VALENCIA, CA 91354 |
| Engineer | Tagudar,, Fred; Lic. No.: C33612 | 255 W 5TH ST APT 706 SAN PEDRO, CA 90731 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/12/2023 | Conditional Approval | CALEB MEISTER |
| Excavation/Setback/Form/Re-Bar | 4/13/2023 | Partial Approval | CALEB MEISTER |
| PLUMBING-Rough | 4/13/2023 | Partial Approval | CALEB MEISTER |
| Sewer | 4/13/2023 | Approved | CALEB MEISTER |
| Excavation/Setback/Form/Re-Bar | 4/19/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 4/19/2023 | Partial Approval | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 5/8/2023 | Not Ready for Inspection | CALEB MEISTER |
| Gas Test | 5/8/2023 | Not Ready for Inspection | CALEB MEISTER |
| MERV13>=Rough | 5/8/2023 | Not Ready for Inspection | CALEB MEISTER |
| METHANE-Rough | 5/8/2023 | Not Ready for Inspection | CALEB MEISTER |
| Rough-Elec/Plmb/HVAC | 5/8/2023 | Not Ready for Inspection | CALEB MEISTER |
| Shower Pan | 5/8/2023 | Not Ready for Inspection | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2023 | Approved | CALEB MEISTER |
| Insulation | 5/11/2023 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 5/11/2023 | Approved | CALEB MEISTER |
| Drywall Nailing | 5/17/2023 | Approved | CALEB MEISTER |
| ELECTRICAL-Final | 5/17/2023 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Final | 5/24/2023 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 6/14/2023 | Approved | CALEB MEISTER |
| Final | 6/14/2023 | Conditional Approval | CALEB MEISTER |
| MERV13>=Final | 6/14/2023 | Approved | CALEB MEISTER |
| MERV13>=Rough | 6/14/2023 | Approved | CALEB MEISTER |
| METHANE-Final | 6/14/2023 | Approved | CALEB MEISTER |
| METHANE-Rough | 6/14/2023 | Approved | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 6/14/2023 | SGSOV Approved | CALEB MEISTER |
| Smoke Detectors | 6/14/2023 | Approved | CALEB MEISTER |
| Final | 8/22/2023 | OK to Issue CofO | CALEB MEISTER |