1125 S WESTMORELAND AVE 90006
Certificate Information: 1125 S WESTMORELAND AVE 90006
- Application / Permit
- 21016-10000-54229
- Plan Check / Job No.
- B21LA21435
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: Install 4 Special Steel Cantilever Columns
- Permit Issued
- Issued on 4/2/2024
- Issuing Office
- Current Status
- CofC Issued on 6/24/2025
Permit Application Status History
| Submitted | 11/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2021 | HANS SANTIAGO |
| Corrections Issued | 1/3/2022 | HANS SANTIAGO |
| Quality Review Completed | 1/10/2022 | SAI KHUM |
| Applicant returned to address corrections | 1/25/2022 | HANS SANTIAGO |
| Plan Check Approved | 1/31/2022 | ANDREW SANTIAGO |
| Issued | 4/2/2024 | APPLICANT |
| OK for CofC | 6/20/2025 | DARRYL ARNOLD |
| CofC Issued | 6/24/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 4/1/2024 | HUGO GARRIDO GARZA |
Contact Information
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | Park,, Kenan; Lic. No.: C86314 | 904 S HARVARD BLVD APT 208 LOS ANGELES, CA 90006 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/31/2024 | Conditional Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 6/25/2024 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 6/25/2024 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 6/26/2024 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 6/28/2024 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 7/3/2024 | Corrections Issued | DARRYL ARNOLD |
| Structural Steel Frame | 7/3/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| Wood Frame | 7/3/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 7/8/2024 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 9/10/2024 | Approved | MARTIN TAVITIAN |
| Final | 6/20/2025 | OK for CofC | DARRYL ARNOLD |
| METHANE-Final | 6/20/2025 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 6/20/2025 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 6/20/2025 | Approved | DARRYL ARNOLD |