835 1/2 E COMMONWEALTH AVE 90291

Certificate Information: 835 1/2 E COMMONWEALTH AVE 90291

Application / Permit
21016-10000-53535
Plan Check / Job No.
B21LA21392
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing garage into an accessory dwelling unit per CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 9/12/2022
Issuing Office
Current Status
CofO Issued on 5/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/18/2021 APPLICANT
Assigned to Plan Check Engineer 11/22/2021 SHANGQIN XIE
Corrections Issued 11/23/2021 SHANGQIN XIE
Plan Check Approved 1/7/2022 FERNANDO FLORES
Issued 9/12/2022 APPLICANT
Building Plans Picked Up 9/14/2022 APPLICANT
CofO in Progress 5/10/2023 EVAN COOPER
Permit Finaled 5/11/2023 DANIEL ORRANTE
CofO Issued 5/11/2023 DANIEL ORRANTE
Permit Finaled 5/11/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/3/2021 ABEL CASILLAS
Sewer availability Cleared 12/3/2021 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 12/9/2021 ABEL CASILLAS
Specific Plan Cleared 12/23/2021 PEDRO AYALA

Contact Information

Contractor Claw And Hammer Inc; Lic. No.: 1024564-B 6310 BUCKLER AVENUE      LOS ANGELES, CA 90043
Engineer Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 2160 PARNELL WY      ALTADENA, CA 91001

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/16/2022 Conditional Approval DAVID FEILER
Footing/Foundation/Slab 9/20/2022 No Access for Inspection DAVID FEILER
Footing/Foundation/Slab 9/22/2022 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 10/12/2022 Approved DAVID FEILER
PLUMBING-Rough 11/7/2022 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 11/21/2022 Corrections Issued DAVID FEILER
ELECTRICAL-Rough 1/24/2023 Approved CLAYTON GRAHAM
HVAC-Rough 1/24/2023 Conditional Approval CLAYTON GRAHAM
PLUMBING-Rough 1/24/2023 Not Ready for Inspection CLAYTON GRAHAM
PLUMBING-Rough 1/26/2023 Approved EVAN COOPER
Underground Mechanical 1/26/2023 Partial Approval EVAN COOPER
Insulation 1/31/2023 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 2/3/2023 Approved EVAN COOPER
Insulation 2/3/2023 Approved EVAN COOPER
Interior/Exterior Lathing 2/3/2023 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 2/7/2023 No Access for Inspection EVAN COOPER
Drywall Nailing 2/13/2023 Approved EVAN COOPER
Interior/Exterior Lathing 2/13/2023 Approved EVAN COOPER
ELECTRICAL-Final 5/2/2023 Approved EVAN COOPER
HVAC-Final 5/2/2023 Corrections Issued EVAN COOPER
PLUMBING-Final 5/2/2023 Corrections Issued EVAN COOPER
Service/Power Release 5/2/2023 Approved EVAN COOPER
BUILDING-Rough-Frame 5/8/2023 Approved EVAN COOPER
Final 5/8/2023 OK to Issue CofO EVAN COOPER
HVAC-Final 5/8/2023 Approved EVAN COOPER
PLUMBING-Final 5/8/2023 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 5/8/2023 SGSOV Approved EVAN COOPER
Smoke Detectors 5/8/2023 Approved EVAN COOPER