1185 N MYRA AVE 90029
Certificate Information: 1185 N MYRA AVE 90029
- Application / Permit
- 21016-10000-53446
- Plan Check / Job No.
- B21LA21354
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: Install new plywood sheathing to existing wood framed walls
- Permit Issued
- Issued on 5/12/2022
- Issuing Office
- Current Status
- CofC Issued on 5/24/2023
Permit Application Status History
| Submitted | 11/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2021 | JESSE VIDUYA |
| Corrections Issued | 12/16/2021 | JESSE VIDUYA |
| Quality Review Completed | 12/22/2021 | HANS SANTIAGO |
| Plan Check Approved | 4/19/2022 | JESSE VIDUYA |
| Issued | 5/12/2022 | APPLICANT |
| OK for CofC | 5/18/2023 | VAHE KELEDJIAN |
| CofC Issued | 5/24/2023 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 5/11/2022 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Par Construction Inc; Lic. No.: 983593-B | 12319 GREENE AVE LOS ANGELES, CA 90066 |
| Engineer | Funk,, David Lyle; Lic. No.: NA5421 | , |
| Engineer | Funk,, David Lyle; Lic. No.: S5421 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/26/2022 | Corrections Issued | BRUCE CAMPBELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2022 | Partial Approval | BRUCE CAMPBELL |
| Wood Frame | 6/24/2022 | Partial Approval | BRUCE CAMPBELL |
| Footing/Foundation/Slab | 6/27/2022 | Corrections Issued | BRUCE CAMPBELL |
| Deputy Wood Construction | 7/14/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Wood Construction | 7/19/2022 | Approved | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 10/5/2022 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 10/7/2022 | Partial Approval | DANIEL VARNUM |
| Deputy Reinf. Concrete | 10/11/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 10/21/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 10/21/2022 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 11/7/2022 | Conditional Approval | DARRYL ARNOLD |
| Wall Anchors | 11/7/2022 | Approved | DARRYL ARNOLD |
| Wood Frame | 11/7/2022 | Approved | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 11/10/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 11/23/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Wood Construction | 11/23/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 11/29/2022 | Conditional Approval | VAHE KELEDJIAN |
| Deputy Wood Construction | 11/29/2022 | Conditional Approval | VAHE KELEDJIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2022 | Partial Approval | BRUCE CAMPBELL |
| Wood Frame | 12/1/2022 | Approved | BRUCE CAMPBELL |
| Deputy Wood Construction | 12/14/2022 | Conditional Approval | DARRYL ARNOLD |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2022 | Partial Approval | VAHE KELEDJIAN |
| Interior/Exterior Lathing | 2/13/2023 | Approved | VAHE KELEDJIAN |
| Final | 5/18/2023 | OK for CofC | VAHE KELEDJIAN |
| SGSOV-Seismic Gas S/O Valve | 5/18/2023 | SGSOV Approved | VAHE KELEDJIAN |
| Smoke Detectors | 5/18/2023 | Approved | VAHE KELEDJIAN |