1019 E 4TH PL 1st & 2nd-Floor 90013

Certificate Information: 1019 E 4TH PL 1st & 2nd-Floor 90013

Application / Permit
21016-10000-53271
Plan Check / Job No.
B21LA21328
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
Tenant Improvement for commercial office. Work includes: interior demolition, interior partitions, suspended ceilings, millwork. No change to existing use or occupancy.
Permit Issued
Issued on 2/14/2022
Issuing Office
Current Status
Permit Finaled on 12/16/2022

Permit Application Status History

Submitted 11/30/2021 APPLICANT
Assigned to Plan Check Engineer 12/16/2021 JOE VO
Corrections Issued 12/19/2021 JOE VO
Quality Review Completed 12/21/2021 LIPING TENG
Applicant returned to address corrections 1/11/2022 JOE VO
Plan Check Approved 2/9/2022 JOE VO
Issued 2/14/2022 APPLICANT
Permit Finaled 12/16/2022 MARK FERRARI

Permit Application Clearance Information

Green Code Cleared 1/13/2022 AARON COSTA
DAS Clearance Cleared 2/2/2022 JOE VO

Contact Information

Architect Fine,, Keith; Lic. No.: C32653 3624 SCHAEFER STREET      CULVER CITY, CA 90232
Contractor Renault And Moran Construction Llc; Lic. No.: 1038156-B 19900 MACARTHUR BLVD STE 600      IRVINE, CA 92612

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/17/2022 Not Ready for Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 2/23/2022 Partial Approval MARK FERRARI
Light Gage Steel Frame 2/25/2022 Not Ready for Inspection MARK FERRARI
Light Gage Steel Frame 2/28/2022 Partial Approval MARK FERRARI
Drywall Nailing 3/8/2022 Partial Approval MARK FERRARI
Light Gage Steel Frame 3/14/2022 Conditional Approval DARRYL ARNOLD
Drywall Nailing 3/17/2022 Partial Approval MARK FERRARI
Light Gage Steel Frame 3/17/2022 Partial Approval MARK FERRARI
Light Gage Steel Frame 3/31/2022 Partial Approval MARK FERRARI
Structural Steel Frame 3/31/2022 Not Ready for Inspection MARK FERRARI
Light Gage Steel Frame 4/7/2022 Partial Approval MARK FERRARI
Structural Steel Frame 4/7/2022 Partial Approval MARK FERRARI
Light Gage Steel Frame 4/11/2022 Partial Approval MARK FERRARI
Light Gage Steel Frame 4/15/2022 Partial Approval MARK FERRARI
Drywall Nailing 4/25/2022 Approved MARK FERRARI
T-Bar Ceiling 4/25/2022 Partial Approval MARK FERRARI
T-Bar Ceiling 5/6/2022 Approved MARK FERRARI
Special/Order Compliance 5/24/2022 Partial Inspection MARK FERRARI
Special/Order Compliance 5/31/2022 Partial Inspection MARK FERRARI
Final 6/3/2022 Not Ready for Inspection MARK FERRARI
Green Building Final 6/3/2022 Not Ready for Inspection MARK FERRARI
SGSOV-Seismic Gas S/O Valve 6/3/2022 SGSOV Approved MARK FERRARI
Smoke Detectors 6/3/2022 Approved MARK FERRARI
Special/Order Compliance 6/3/2022 Not Ready for Inspection MARK FERRARI
Final 6/8/2022 Corrections Issued MARK FERRARI
Green Building Final 6/8/2022 Partial Approval MARK FERRARI
Final 12/15/2022 Conditional Approval MARK FERRARI
Green Building Final 12/15/2022 Approved MARK FERRARI
Final 12/16/2022 Permit Finaled MARK FERRARI