515 S FIGUEROA ST 90071
Certificate Information: 515 S FIGUEROA ST 90071
- Application / Permit
- 21016-10000-53056
- Plan Check / Job No.
- B21LA21247
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- ePlan This project consists of update to existing restrooms, corridor and lobby on the 19th floor - new interior finishes.
- Permit Issued
- Issued on 3/23/2022
- Issuing Office
- Current Status
- Permit Finaled on 6/24/2022
Permit Application Status History
| Submitted | 11/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2021 | JOE VO |
| Corrections Issued | 11/12/2021 | JOE VO |
| Applicant returned to address corrections | 12/1/2021 | JOE VO |
| Plan Check Approved | 3/21/2022 | JOE VO |
| Issued | 3/23/2022 | APPLICANT |
| Permit Finaled | 6/23/2022 | MARK FERRARI |
Permit Application Clearance Information
| DAS Clearance | Cleared | 3/15/2022 | JOE VO |
| Fire Marshal Fire Life Safety | Cleared | 3/22/2022 | ANDREW KO |
Contact Information
| Contractor | Environmental Contracting Corporation; Lic. No.: 491028-B | , |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 4/19/2022 | Partial Approval | TIMOTHY BUXTON |
| Light Gage Steel Frame | 4/27/2022 | Approved | TIMOTHY BUXTON |
| Drywall Nailing | 5/2/2022 | Approved | TIMOTHY BUXTON |
| T-Bar Ceiling | 5/10/2022 | Approved | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 6/14/2022 | SGSOV No Gas | TIMOTHY BUXTON |
| Final | 6/23/2022 | Permit Finaled | MARK FERRARI |
| Smoke Detectors | 6/23/2022 | Approved | MARK FERRARI |