1025 N MARIPOSA AVE 90029
Certificate Information: 1025 N MARIPOSA AVE 90029
- Application / Permit
- 21016-10000-53007
- Plan Check / Job No.
- B21LA21208
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93:(N) SCCS AND OMF
- Permit Issued
- Issued on 2/22/2022
- Issuing Office
- Current Status
- CofC Issued on 1/20/2023
Permit Application Status History
| Submitted | 11/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/16/2021 | VARAND SARKISIAN |
| Corrections Issued | 11/23/2021 | VARAND SARKISIAN |
| Quality Review Completed | 11/29/2021 | HANS SANTIAGO |
| Plan Check Approved | 1/4/2022 | VARAND SARKISIAN |
| Issued | 2/22/2022 | APPLICANT |
| Permit Finaled-Status Void | 1/20/2023 | WINSTON DUNNING |
| Re-Activate Permit | 1/20/2023 | WINSTON DUNNING |
| OK for CofC | 1/20/2023 | WINSTON DUNNING |
| CofC Issued | 1/20/2023 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 2/15/2022 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | H Z S Construction; Lic. No.: 1039476-B | 1720 E GARRY AVE #229 SANTA ANA, CA 92705 |
| Engineer | Shekaramiz,, Hamid; Lic. No.: C82784 | 2 TIMBRE RANCHO SANTA MARGARITA, CA 92688 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/25/2022 | Conditional Approval | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 3/2/2022 | Approved | BRUCE CAMPBELL |
| Pre-Inspection | 3/2/2022 | Approved | BRUCE CAMPBELL |
| Deputy Reinf. Concrete | 3/8/2022 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Steel/Welding | 3/18/2022 | Conditional Approval | BRUCE CAMPBELL |
| Wood Frame | 3/25/2022 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Wood Construction | 3/30/2022 | Conditional Approval | BRUCE CAMPBELL |
| Wood Frame | 3/30/2022 | Approved | BRUCE CAMPBELL |
| Interior/Exterior Lathing | 4/14/2022 | Conditional Approval | BRUCE CAMPBELL |
| Final | 5/4/2022 | Not Ready for Inspection | BRUCE CAMPBELL |
| SGSOV-Seismic Gas S/O Valve | 5/4/2022 | SGSOV Not Ready | BRUCE CAMPBELL |
| SGSOV-Seismic Gas S/O Valve | 5/12/2022 | SGSOV Not Ready | BRUCE CAMPBELL |
| Pre-Inspection | 5/13/2022 | Approved | JONATHAN QUACH |
| Final | 1/20/2023 | OK for CofC | WINSTON DUNNING |
| SGSOV-Seismic Gas S/O Valve | 1/20/2023 | SGSOV Approved | WINSTON DUNNING |
| Smoke Detectors | 1/20/2023 | Approved | WINSTON DUNNING |