18028 W DUNCAN ST 91316

Certificate Information: 18028 W DUNCAN ST 91316

Application / Permit
21016-10000-52953
Plan Check / Job No.
B21LA21182
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO DETACHED ADU PER STATE LAW (1-STORY)
Permit Issued
Issued on 3/15/2022
Issuing Office
Current Status
CofO Issued on 4/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/9/2021 APPLICANT
Assigned to Plan Check Engineer 11/11/2021 JOE VO
Corrections Issued 11/11/2021 CARLOS MONTES
Applicant returned to address corrections 2/21/2022 JOE VO
Plan Check Approved 3/7/2022 JOE VO
Issued 3/15/2022 APPLICANT
CofO in Progress 4/24/2023 JEFFREY BULL
CofO Issued 4/25/2023 MICHAEL SMITH
Permit Finaled 4/25/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/18/2021 CARLOS AGUILERA
Sewer availability Cleared 11/18/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/20/2021 CARLOS AGUILERA
Construction within easement Cleared 2/18/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/16/2022 Conditional Approval JUSTIN HAWLEY
Excavation/Setback/Form/Re-Bar 5/18/2022 Approved VINCENT HANLEY
Footing/Foundation/Slab 5/18/2022 Approved VINCENT HANLEY
PLUMBING-Rough 5/18/2022 Partial Approval VINCENT HANLEY
Sewer 5/18/2022 Approved VINCENT HANLEY
Deputy Drilled-In Anchors 6/8/2022 Conditional Approval MORRIS JACKSON
Wood Frame 6/9/2022 Partial Approval JESUS PINEDA
ELECTRICAL-Rough 6/21/2022 Partial Approval JEFFREY BULL
Insulation 6/21/2022 Approved JEFFREY BULL
Wood Frame 6/29/2022 Approved JEFFREY BULL
ELECTRICAL-Rough 7/1/2022 Approved JEFFREY BULL
PLUMBING-Rough 7/1/2022 Not Ready for Inspection JEFFREY BULL
Gas Test 7/8/2022 Not Ready for Inspection DAVID SANDOVAL
Interior/Exterior Lathing 7/8/2022 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 7/8/2022 Corrections Issued DAVID SANDOVAL
Gas Test 7/14/2022 Approved JEFFREY BULL
Interior/Exterior Lathing 7/14/2022 Approved JEFFREY BULL
PLUMBING-Rough 7/14/2022 Approved JEFFREY BULL
HVAC-Rough 7/18/2022 Approved JEFFREY BULL
Drywall Nailing 7/21/2022 Approved JUSTIN HAWLEY
Insulation 7/21/2022 Approved JUSTIN HAWLEY
Underground Mechanical 10/7/2022 No Access for Inspection SEAN HAUPT
Underground Mechanical 10/31/2022 Approved JEFFREY BULL
ELECTRICAL-Final 11/7/2022 Not Ready for Inspection JEFFREY BULL
Final 11/7/2022 Corrections Issued JEFFREY BULL
Gas Test 11/7/2022 Approved JEFFREY BULL
HVAC-Final 11/7/2022 Approved JEFFREY BULL
PLUMBING-Final 11/7/2022 Approved JEFFREY BULL
BUILDING-Rough-Frame 12/30/2022 Approved JEFFREY BULL
FLOOD-Proofing Certificate 12/30/2022 Approved JEFFREY BULL
Final 12/30/2022 Corrections Issued JEFFREY BULL
Green Building Final 12/30/2022 Approved JEFFREY BULL
Green Building Rough 12/30/2022 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 12/30/2022 SGSOV Not Ready JEFFREY BULL
Smoke Detectors 12/30/2022 Approved JEFFREY BULL
Final 1/13/2023 No Access for Inspection JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 1/13/2023 SGSOV Not Ready JEFFREY PARD
Final 1/20/2023 Not Ready for Inspection JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 1/20/2023 SGSOV Approved JEFFREY BULL
Service/Power Release 1/20/2023 Approved JEFFREY BULL
ELECTRICAL-Final 4/24/2023 Approved JEFFREY BULL
Final 4/24/2023 OK to Issue CofO JEFFREY BULL