3872 S EAST BLVD 90066

Certificate Information: 3872 S EAST BLVD 90066

Application / Permit
21016-10000-52791
Plan Check / Job No.
B21LA21124
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert and alter existing carport into a new detached ADU
Permit Issued
Issued on 3/3/2022
Issuing Office
Current Status
CofO Issued on 8/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/8/2021 APPLICANT
Assigned to Plan Check Engineer 11/11/2021 JOE VO
Corrections Issued 11/11/2021 JOE VO
Applicant returned to address corrections 12/7/2021 JOE VO
Applicant returned to address corrections 12/8/2021 JOE VO
Plan Check Approved 2/8/2022 JOE VO
Issued 3/3/2022 APPLICANT
CofO in Progress 8/25/2023 JESUS RODRIGUEZ
Permit Finaled 8/29/2023 DANIEL ORRANTE
CofO Issued 8/29/2023 DANIEL ORRANTE
Permit Finaled 8/29/2023 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 11/30/2021 VALERIA CEJA
Address approval Cleared 12/6/2021 DINAH GARIN
Roof/Waste drainage to street Cleared 12/6/2021 DINAH GARIN
Sewer availability Cleared 12/6/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 12/8/2021 DINAH GARIN
Hydrant and Access approval Cleared 2/7/2022 MATTHEW CRAIG

Contact Information

Contractor Zeng Yanfen; Lic. No.: 1054615-B 11627 RIO HONDO PKWAY      EL MONTE, CA 91732

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/11/2022 Corrections Issued PATRICK QUALEY
PLUMBING-Rough 5/16/2022 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 5/19/2022 Corrections Issued PATRICK QUALEY
Pre-Inspection 5/25/2022 Partial Inspection PATRICK QUALEY
Footing/Foundation/Slab 6/6/2022 Corrections Issued PATRICK QUALEY
Footing/Foundation/Slab 6/7/2022 Conditional Approval PATRICK QUALEY
Pre-Inspection 6/30/2022 Corrections Issued JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 7/14/2022 Conditional Approval PATRICK QUALEY
Footing/Foundation/Slab 7/14/2022 Conditional Approval PATRICK QUALEY
Footing/Foundation/Slab 8/18/2022 Approved STEPHANIE SWANSON
ELECTRICAL-Rough 10/19/2022 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/19/2022 Conditional Approval JESUS RODRIGUEZ
PLUMBING-Rough 10/19/2022 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 4/10/2023 Approved JESUS PINEDA
Shower Pan 4/10/2023 Corrections Issued JESUS PINEDA
BUILDING-Rough-Frame 4/13/2023 Partial Inspection JESUS RODRIGUEZ
Green Building Rough 4/13/2023 Approved JESUS RODRIGUEZ
HVAC-Rough 4/13/2023 Partial Approval JESUS RODRIGUEZ
Interior/Exterior Lathing 4/13/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 4/13/2023 Corrections Issued JESUS RODRIGUEZ
Shower Pan 4/13/2023 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 4/19/2023 Approved JESUS RODRIGUEZ
Insulation 4/19/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 4/19/2023 Approved JESUS RODRIGUEZ
Drywall Nailing 4/27/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 6/28/2023 Corrections Issued JESUS RODRIGUEZ
Final 6/28/2023 Corrections Issued JESUS RODRIGUEZ
Green Building Final 6/28/2023 Approved JESUS RODRIGUEZ
HVAC-Final 6/28/2023 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 6/28/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 6/28/2023 SGSOV Not Ready JESUS RODRIGUEZ
Smoke Detectors 6/28/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 8/16/2023 Approved HERBERT GIRON
Final 8/16/2023 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 8/16/2023 SGSOV Not Ready HERBERT GIRON
Final 8/22/2023 Partial Approval JESUS RODRIGUEZ
HVAC-Final 8/22/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 8/22/2023 SGSOV Approved JESUS RODRIGUEZ
Final 8/25/2023 Conditional Approval JESUS RODRIGUEZ