3872 S EAST BLVD 90066
Certificate Information: 3872 S EAST BLVD 90066
- Application / Permit
- 21016-10000-52791
- Plan Check / Job No.
- B21LA21124
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert and alter existing carport into a new detached ADU
- Permit Issued
- Issued on 3/3/2022
- Issuing Office
- Current Status
- CofO Issued on 8/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/11/2021 | JOE VO |
| Corrections Issued | 11/11/2021 | JOE VO |
| Applicant returned to address corrections | 12/7/2021 | JOE VO |
| Applicant returned to address corrections | 12/8/2021 | JOE VO |
| Plan Check Approved | 2/8/2022 | JOE VO |
| Issued | 3/3/2022 | APPLICANT |
| CofO in Progress | 8/25/2023 | JESUS RODRIGUEZ |
| Permit Finaled | 8/29/2023 | DANIEL ORRANTE |
| CofO Issued | 8/29/2023 | DANIEL ORRANTE |
| Permit Finaled | 8/29/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 11/30/2021 | VALERIA CEJA |
| Address approval | Cleared | 12/6/2021 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 12/6/2021 | DINAH GARIN |
| Sewer availability | Cleared | 12/6/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 12/8/2021 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 2/7/2022 | MATTHEW CRAIG |
Contact Information
| Contractor | Zeng Yanfen; Lic. No.: 1054615-B | 11627 RIO HONDO PKWAY EL MONTE, CA 91732 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/11/2022 | Corrections Issued | PATRICK QUALEY |
| PLUMBING-Rough | 5/16/2022 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 5/19/2022 | Corrections Issued | PATRICK QUALEY |
| Pre-Inspection | 5/25/2022 | Partial Inspection | PATRICK QUALEY |
| Footing/Foundation/Slab | 6/6/2022 | Corrections Issued | PATRICK QUALEY |
| Footing/Foundation/Slab | 6/7/2022 | Conditional Approval | PATRICK QUALEY |
| Pre-Inspection | 6/30/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 7/14/2022 | Conditional Approval | PATRICK QUALEY |
| Footing/Foundation/Slab | 7/14/2022 | Conditional Approval | PATRICK QUALEY |
| Footing/Foundation/Slab | 8/18/2022 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 10/19/2022 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2022 | Conditional Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 10/19/2022 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 4/10/2023 | Approved | JESUS PINEDA |
| Shower Pan | 4/10/2023 | Corrections Issued | JESUS PINEDA |
| BUILDING-Rough-Frame | 4/13/2023 | Partial Inspection | JESUS RODRIGUEZ |
| Green Building Rough | 4/13/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 4/13/2023 | Partial Approval | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 4/13/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 4/13/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Shower Pan | 4/13/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 4/19/2023 | Approved | JESUS RODRIGUEZ |
| Insulation | 4/19/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 4/19/2023 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 4/27/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 6/28/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 6/28/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 6/28/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 6/28/2023 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Final | 6/28/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 6/28/2023 | SGSOV Not Ready | JESUS RODRIGUEZ |
| Smoke Detectors | 6/28/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 8/16/2023 | Approved | HERBERT GIRON |
| Final | 8/16/2023 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 8/16/2023 | SGSOV Not Ready | HERBERT GIRON |
| Final | 8/22/2023 | Partial Approval | JESUS RODRIGUEZ |
| HVAC-Final | 8/22/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 8/22/2023 | SGSOV Approved | JESUS RODRIGUEZ |
| Final | 8/25/2023 | Conditional Approval | JESUS RODRIGUEZ |