110 E 9TH ST 1300-BLDG A&B 90015

Certificate Information: 110 E 9TH ST 1300-BLDG A&B 90015

Application / Permit
21016-10000-52725
Plan Check / Job No.
B21LA21101
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
eplan. THE SCOPE OF WORK OCCURS ON LEVELS 2 AND 13 AND IS TO INCLUDE, BUT IS NOT LIMITED TO: NEW NON-LOAD BEARING PARTITIONS, DOORS, CEILINGS, FINISHES, THERE IS NO CHANGE OF USE OR OCCUPANCY TYPE ASSOCIATED WITH PROJECT SCOPE.
Permit Issued
Issued on 3/14/2022
Issuing Office
Current Status
Permit Finaled on 3/22/2024

Permit Application Status History

Submitted 11/10/2021 APPLICANT
Assigned to Plan Check Engineer 11/12/2021 LARRY LEE
Corrections Issued 11/15/2021 LARRY LEE
Plan Check Approved 2/25/2022 LARRY LEE
Issued 3/14/2022 APPLICANT
Permit Finaled 3/22/2024 NICK DANERI

Permit Application Clearance Information

Fire Marshal Fire Life Safety Cleared 2/8/2022 MENOA AGHAJANI

Contact Information

Architect Baptista,, Braulio Magno; Lic. No.: C35840 515 S FLOWER STREET SUITE 3700      LOS ANGELES, CA 90071
Contractor Swinerton Builders; Lic. No.: 92-B 2001 CLAYTON RD   7TH FLOOR LEGAL    CONCORD, CA 94529
Engineer Monnier,, Anne Birgitte; Lic. No.: S5091 111 SW 5TH AVENUE SUITE 2500      PORTLAND, OR 97204

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/25/2022 Approved JONATHAN QUACH
Pre-Inspection 4/4/2022 Approved KATY RAMIREZ
Deputy Steel/Welding 4/5/2022 Conditional Approval KATY RAMIREZ
Deputy Fireproofing 4/8/2022 Conditional Approval KATY RAMIREZ
Deputy Fireproofing 4/12/2022 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 4/15/2022 Conditional Approval KATY RAMIREZ
Light Gage Steel Frame 4/18/2022 Partial Approval TIMOTHY BUXTON
Deputy Fireproofing 4/19/2022 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 4/19/2022 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 4/20/2022 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 4/20/2022 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 4/20/2022 Conditional Approval KATY RAMIREZ
Light Gage Steel Frame 4/20/2022 Partial Approval KATY RAMIREZ
Deputy Drilled-In Anchors 4/21/2022 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 4/21/2022 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 4/21/2022 Conditional Approval KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 4/22/2022 Partial Approval KATY RAMIREZ
Deputy Reinf. Concrete 4/26/2022 Conditional Approval KATY RAMIREZ
Drywall Nailing 4/26/2022 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 4/26/2022 Partial Approval KATY RAMIREZ
Deputy Drilled-In Anchors 4/27/2022 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 4/27/2022 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 4/27/2022 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 4/28/2022 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 4/29/2022 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 4/29/2022 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 4/29/2022 Conditional Approval KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 4/29/2022 Partial Approval KATY RAMIREZ
Deputy Drilled-In Anchors 5/2/2022 Conditional Approval TIMOTHY BUXTON
Deputy Fireproofing 5/2/2022 Conditional Approval TIMOTHY BUXTON
Deputy Reinf. Concrete 5/2/2022 Conditional Approval TIMOTHY BUXTON
Insulation 5/4/2022 Partial Approval KATY RAMIREZ
Deputy Fireproofing 5/10/2022 Conditional Approval KATY RAMIREZ
Drywall Nailing 5/11/2022 Partial Approval KATY RAMIREZ
Deputy Steel/Welding 5/12/2022 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 5/13/2022 Conditional Approval KATY RAMIREZ
Deputy Fireproofing 5/18/2022 Conditional Approval KATY RAMIREZ
Light Gage Steel Frame 5/24/2022 Partial Approval KATY RAMIREZ
Pre-Inspection 5/26/2022 Approved TIMOTHY BUXTON
Reinforced Concrete Frame 6/1/2022 No Access for Inspection KATY RAMIREZ
Deputy Steel/Welding 6/2/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/3/2022 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 6/3/2022 Conditional Approval ERNESTO CORRAL
Light Gage Steel Frame 6/3/2022 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 6/7/2022 Partial Inspection KATY RAMIREZ
Reinforced Concrete Frame 6/7/2022 Corrections Issued KATY RAMIREZ
Deputy Fireproofing 6/8/2022 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 6/8/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/9/2022 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 6/9/2022 Conditional Approval KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 6/9/2022 Partial Approval KATY RAMIREZ
Deputy Drilled-In Anchors 6/10/2022 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 6/10/2022 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 6/10/2022 Conditional Approval KATY RAMIREZ
Drywall Nailing 6/10/2022 Partial Approval KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 6/10/2022 Partial Approval KATY RAMIREZ
Deputy Drilled-In Anchors 6/13/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/13/2022 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 6/22/2022 Conditional Approval ERNESTO CORRAL
Light Gage Steel Frame 6/23/2022 Partial Approval BRUCE CAMPBELL
Deputy Steel/Welding 7/1/2022 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 7/6/2022 Approved TIMOTHY BUXTON
Excavation/Setback/Form/Re-Bar 7/7/2022 Partial Approval NICK DANERI
Deputy Reinf. Concrete 7/8/2022 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 7/8/2022 Conditional Approval ERNESTO CORRAL
Drywall Nailing 7/11/2022 Approved TIMOTHY BUXTON
Insulation 7/11/2022 Approved TIMOTHY BUXTON
Light Gage Steel Frame 7/11/2022 Approved TIMOTHY BUXTON
Deputy Drilled-In Anchors 7/12/2022 Conditional Approval TIMOTHY BUXTON
Deputy Steel/Welding 7/12/2022 Conditional Approval TIMOTHY BUXTON
Deputy Steel/Welding 7/14/2022 Conditional Approval ERNESTO CORRAL
Drywall Nailing 7/15/2022 Partial Inspection RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 7/15/2022 Partial Inspection RAFAEL ESPINOZA
Structural Steel Frame 7/15/2022 Partial Approval RAFAEL ESPINOZA
Final 7/24/2022 Off-Hour Fees Due
SGSOV-Seismic Gas S/O Valve 7/24/2022 Off-Hour Fees Due
Smoke Detectors 7/24/2022 Off-Hour Fees Due
Special/Order Compliance 7/25/2022 Not Ready for Inspection KATY RAMIREZ
Special/Order Compliance 8/2/2022 Approved KATY RAMIREZ
Special/Order Compliance 8/17/2022 Not Ready for Inspection KATY RAMIREZ
Special/Order Compliance 8/26/2022 Not Ready for Inspection KATY RAMIREZ
Special/Order Compliance 8/31/2022 Partial Inspection KATY RAMIREZ
Insulation 10/3/2022 No Access for Inspection KATY RAMIREZ
Special/Order Compliance 12/1/2022 Conditional Approval TED RIES
Special/Order Compliance 12/6/2022 Not Ready for Inspection KATY RAMIREZ
Special/Order Compliance 12/12/2022 Approved KATY RAMIREZ
Insulation 9/8/2023 Partial Approval JULIAN CAPUCETTI
Special/Order Compliance 9/22/2023 Not Ready for Inspection KATY RAMIREZ
Final 3/22/2024 Permit Finaled NICK DANERI
SGSOV-Seismic Gas S/O Valve 3/22/2024 SGSOV Approved NICK DANERI
Smoke Detectors 3/22/2024 Approved NICK DANERI