6212 S VAN NESS AVE 90047

Certificate Information: 6212 S VAN NESS AVE 90047

Application / Permit
21016-10000-52713
Plan Check / Job No.
B21LA21097
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLAN. CONVERT (E) DETACHED GARAGE TO AN ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 1/13/2022
Issuing Office
Current Status
CofO Issued on 12/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2021 APPLICANT
Assigned to Plan Check Engineer 11/15/2021 KEVIN MORALES
Corrections Issued 11/15/2021 KEVIN MORALES
Applicant returned to address corrections 1/6/2022 KEVIN MORALES
Plan Check Approved 1/10/2022 KEVIN MORALES
Issued 1/13/2022 APPLICANT
CofO in Progress 9/8/2022 ENRIQUE MIRELES
Permit Finaled 12/1/2022 DEROLD HAUFF
CofO Issued 12/1/2022 DEROLD HAUFF
Permit Finaled 12/1/2022 DEROLD HAUFF

Permit Application Clearance Information

ZA Case Cleared 11/17/2021 DANIEL CORONADO
Address approval Cleared 11/19/2021 CHRISTOPHER ROCHA
Sewer availability Cleared 11/19/2021 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 1/5/2022 CHRISTOPHER ROCHA

Contact Information

Contractor Retrofitting360 Inc; Lic. No.: 1039226-B 19562 VENTURA BLVD# 230      TARZANA, CA 91356

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/20/2022 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 1/25/2022 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 2/25/2022 Corrections Issued FREDDIE RIVERA
Wood Frame 2/25/2022 Partial Inspection FREDDIE RIVERA
Wood Frame 3/24/2022 Corrections Issued ENRIQUE MIRELES
Deputy Wood Construction 3/25/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 4/5/2022 Not Ready for Inspection ENRIQUE MIRELES
HVAC-Rough 4/5/2022 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 4/5/2022 Not Ready for Inspection ENRIQUE MIRELES
Wood Frame 4/5/2022 Partial Approval ENRIQUE MIRELES
ELECTRICAL-Rough 4/8/2022 Approved ENRIQUE MIRELES
HVAC-Rough 4/8/2022 Approved ENRIQUE MIRELES
PLUMBING-Rough 4/8/2022 Approved ENRIQUE MIRELES
Wood Frame 4/8/2022 Approved ENRIQUE MIRELES
Insulation 4/12/2022 Approved ENRIQUE MIRELES
Drywall Nailing 4/21/2022 Approved ENRIQUE MIRELES
Sewer 5/26/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 8/31/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Final 8/31/2022 Approved ENRIQUE MIRELES
Final 8/31/2022 Corrections Issued ENRIQUE MIRELES
HVAC-Final 8/31/2022 Approved ENRIQUE MIRELES
PLUMBING-Final 8/31/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 8/31/2022 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 8/31/2022 Approved ENRIQUE MIRELES
Final 9/7/2022 OK to Issue CofO ENRIQUE MIRELES